Gokul Heights

by SEEMA VIJAY NIKAM · Ajivali, Raigarh

Registered on MahaRERA under P52000052367. Status: Completed. Its completion date has moved from June 2025 to June 2026, 12 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Gokul Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000052367
Status
Completed
Builder
SEEMA VIJAY NIKAM
Location
Ajivali, Raigarh · 410221
Project type
Residential / Group Housing
Registered on
21 Aug 2023
Completion date at registration
June 2025
Latest completion date
June 2026
Delay so far
12 months
Homes
56
Sold or booked
89%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Kundli Watch

Gokul Heights: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Gokul Heights

Is Gokul Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gokul Heights is registered as P52000052367 and its status is "Completed".

Where is Gokul Heights?

Gokul Heights by SEEMA VIJAY NIKAM is in Ajivali, Raigarh (pincode 410221), Maharashtra, and is registered on MahaRERA as P52000052367, per GharKundli's check of MahaRERA records.

When is possession of Gokul Heights due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gokul Heights in Ajivali, Raigarh is 30 June 2026 — 12 months later than 30 June 2025, the date given at registration.

Does Gokul Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Gokul Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SEEMA VIJAY NIKAM, which has 1 other project registered on MahaRERA.

Other projects in pincode 410221

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.