ARIHANT ASPIRE PHASE IV
by ARIHANT ABODE LIMITED · Palaspe, Raigarh
Registered on MahaRERA under PR1274042502314, and currently active. Its completion date has moved from March 2032 to July 2032, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on ARIHANT ASPIRE PHASE IV
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1274042502314
- Status
- Registered and active
- Builder
- ARIHANT ABODE LIMITED
- Location
- Palaspe, Raigarh · 410221
- Project type
- Residential / Group Housing
- Registered on
- 10 Feb 2026
- Completion date at registration
- March 2032
- Latest completion date
- July 2032
- Delay so far
- 4 months
- Homes
- 361
- Sold or booked
- 31%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Kundli Watch
ARIHANT ASPIRE PHASE IV: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about ARIHANT ASPIRE PHASE IV
Is ARIHANT ASPIRE PHASE IV registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ASPIRE PHASE IV is registered as PR1274042502314 and its status is "Registered and active".
Where is ARIHANT ASPIRE PHASE IV?
ARIHANT ASPIRE PHASE IV by ARIHANT ABODE LIMITED is in Palaspe, Raigarh (pincode 410221), Maharashtra, and is registered on MahaRERA as PR1274042502314, per GharKundli's check of MahaRERA records.
When is possession of ARIHANT ASPIRE PHASE IV due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARIHANT ASPIRE PHASE IV in Palaspe, Raigarh is 31 July 2032 — 4 months later than 31 March 2032, the date given at registration.
Does ARIHANT ASPIRE PHASE IV have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of ARIHANT ASPIRE PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT ABODE LIMITED, which has 3 other projects registered on MahaRERA.
Other projects in pincode 410221
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.