Pankaj Aasmaan Phase III

by Pankaj Developers · Sant Nagar, Pune

Registered on MahaRERA under P52100016512, and currently active. Its completion date has moved from October 2021 to April 2027: 62 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Pankaj Aasmaan Phase III

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100016512
Status
Registered and active
Builder
Pankaj Developers
Location
Sant Nagar, Pune · 411047
Project type
Residential / Group Housing
Registered on
21 May 2018
Completion date at registration
October 2021
Latest completion date
April 2027
Delay so far
62 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
120
Sold or booked
99%
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Kundli Watch

Pankaj Aasmaan Phase III: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Pankaj Aasmaan Phase III

Is Pankaj Aasmaan Phase III registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Pankaj Aasmaan Phase III is registered as P52100016512 and its status is "Registered and active".

Where is Pankaj Aasmaan Phase III?

Pankaj Aasmaan Phase III by Pankaj Developers is in Sant Nagar, Pune (pincode 411047), Maharashtra, and is registered on MahaRERA as P52100016512, per GharKundli's check of MahaRERA records.

When is possession of Pankaj Aasmaan Phase III due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pankaj Aasmaan Phase III in Sant Nagar, Pune is 30 April 2027 — 62 months later than 1 October 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Does Pankaj Aasmaan Phase III have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Pankaj Aasmaan Phase III?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pankaj Developers, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2027 in Pune →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.