Shree Saai Forrtune
by Mrunali Realty LLP · Dighi Camp, Pune
Registered on MahaRERA under P52100047346, and currently active. Its completion date has moved from December 2026 to April 2028, 16 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Shree Saai Forrtune
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100047346
- Status
- Registered and active
- Builder
- Mrunali Realty LLP
- Location
- Dighi Camp, Pune · 411015
- Project type
- Others
- Registered on
- 20 Oct 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2028
- Delay so far
- 16 months
- Homes
- 264
- Sold or booked
- 53%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Kundli Watch
Shree Saai Forrtune: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Shree Saai Forrtune
Is Shree Saai Forrtune registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Saai Forrtune is registered as P52100047346 and its status is "Registered and active".
Where is Shree Saai Forrtune?
Shree Saai Forrtune by Mrunali Realty LLP is in Dighi Camp, Pune (pincode 411015), Maharashtra, and is registered on MahaRERA as P52100047346, per GharKundli's check of MahaRERA records.
When is possession of Shree Saai Forrtune due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Saai Forrtune in Dighi Camp, Pune is 30 April 2028 — 16 months later than 30 December 2026, the date given at registration.
Does Shree Saai Forrtune have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Shree Saai Forrtune?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mrunali Realty LLP, which has 2 other projects registered on MahaRERA.
Other projects in pincode 411015
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.