Registered on MahaRERA under PR1260002600977, and currently active. Its completion date has moved from December 2031 to April 2032, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on VASUNDHARA RAJ
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1260002600977
- Status
- Registered and active
- Builder
- VASUNDHARA RAJ
- Location
- Gautam Baug, Pune · 413102
- Project type
- Residential / Group Housing
- Registered on
- 29 Jun 2026
- Completion date at registration
- December 2031
- Latest completion date
- April 2032
- Delay so far
- 4 months
- Homes
- 25
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
VASUNDHARA RAJ: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about VASUNDHARA RAJ
Is VASUNDHARA RAJ registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VASUNDHARA RAJ is registered as PR1260002600977 and its status is "Registered and active".
Where is VASUNDHARA RAJ?
VASUNDHARA RAJ by VASUNDHARA RAJ is in Gautam Baug, Pune (pincode 413102), Maharashtra, and is registered on MahaRERA as PR1260002600977, per GharKundli's check of MahaRERA records.
When is possession of VASUNDHARA RAJ due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VASUNDHARA RAJ in Gautam Baug, Pune is 30 April 2032 — 4 months later than 31 December 2031, the date given at registration.
Does VASUNDHARA RAJ have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of VASUNDHARA RAJ?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VASUNDHARA RAJ.