Astonia Royale Phase II - K and L Building
by AMIT ENTERPRISES HOUSING LIMITED · Ambegaon Bk, PuneAlso near Ambegaon Bk DSO
Registered on MahaRERA under P52100001124. Status: Completed. Its completion date has moved from December 2021 to September 2025, 45 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Astonia Royale Phase II - K and L Building
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100001124
- Status
- Completed
- Builder
- AMIT ENTERPRISES HOUSING LIMITED
- Location
- Ambegaon Bk, Pune · 411046
- Project type
- Residential / Group Housing
- Registered on
- 26 Jul 2017
- Completion date at registration
- December 2021
- Latest completion date
- September 2025
- Delay so far
- 45 months
- Homes
- 165
- Sold or booked
- 88%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Kundli Watch
Astonia Royale Phase II - K and L Building: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Astonia Royale Phase II - K and L Building
Is Astonia Royale Phase II - K and L Building registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Astonia Royale Phase II - K and L Building is registered as P52100001124 and its status is "Completed".
Where is Astonia Royale Phase II - K and L Building?
Astonia Royale Phase II - K and L Building by AMIT ENTERPRISES HOUSING LIMITED is in Ambegaon Bk, Pune (pincode 411046), near Ambegaon Bk DSO, Maharashtra, and is registered on MahaRERA as P52100001124, per GharKundli's check of MahaRERA records.
When is possession of Astonia Royale Phase II - K and L Building due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Astonia Royale Phase II - K and L Building in Ambegaon Bk, Pune is 30 September 2025 — 45 months later than 31 December 2021, the date given at registration.
Does Astonia Royale Phase II - K and L Building have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Astonia Royale Phase II - K and L Building?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AMIT ENTERPRISES HOUSING LIMITED, which has 7 other projects registered on MahaRERA.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.