Skip to content
GharKundli

SAI PARADISE

by ADITYA ASSOCIATES · Indrayani Colony, PuneAlso near Talegaon G H

Registered on MahaRERA under P52100076594, and currently active. Its completion date is now March 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on SAI PARADISE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100076594
Status
Registered and active
Builder
ADITYA ASSOCIATES
Location
Indrayani Colony, Pune · 410507
Project type
Others
Registered on
18 Jun 2024
Completion date at registration
November 2027
Latest completion date
March 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
36
Sold or booked
89%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
25

Kundli Watch

SAI PARADISE: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about SAI PARADISE

Is SAI PARADISE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI PARADISE is registered as P52100076594 and its status is "Registered and active".

Where is SAI PARADISE?

SAI PARADISE by ADITYA ASSOCIATES is in Indrayani Colony, Pune (pincode 410507), near Talegaon G H, Maharashtra, and is registered on MahaRERA as P52100076594, per GharKundli's check of MahaRERA records.

When is possession of SAI PARADISE due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI PARADISE in Indrayani Colony, Pune is 24 March 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Does SAI PARADISE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of SAI PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADITYA ASSOCIATES, which has 25 other projects registered on MahaRERA.

All projects with possession due in 2028 in Pune →

Other projects in pincode 410507

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.