Mainland Valencia Phase II

by MAINLAND BUILDERS LLP · Wagholi, Pune

Registered on MahaRERA under P52100024109, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Mainland Valencia Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100024109
Status
Registered and active
Builder
MAINLAND BUILDERS LLP
Location
Wagholi, Pune · 412207
Project type
Commercial
Registered on
21 Jan 2020
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
66%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Kundli Watch

Mainland Valencia Phase II: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Mainland Valencia Phase II

Is Mainland Valencia Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mainland Valencia Phase II is registered as P52100024109 and its status is "Registered and active".

Where is Mainland Valencia Phase II?

Mainland Valencia Phase II by MAINLAND BUILDERS LLP is in Wagholi, Pune (pincode 412207), Maharashtra, and is registered on MahaRERA as P52100024109, per GharKundli's check of MahaRERA records.

When is possession of Mainland Valencia Phase II due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mainland Valencia Phase II in Wagholi, Pune is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Does Mainland Valencia Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Mainland Valencia Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAINLAND BUILDERS LLP, which has 1 other project registered on MahaRERA.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.