VERTICA PHASE 2

by V Realty · Balewadi, Pune

Registered on MahaRERA under P52100034995, and currently active. Its completion date has moved from March 2026 to April 2029, 37 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on VERTICA PHASE 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100034995
Status
Registered and active
Builder
V Realty
Location
Balewadi, Pune · 411045
Project type
Commercial
Registered on
28 Apr 2022
Completion date at registration
March 2026
Latest completion date
April 2029
Delay so far
37 months
Homes
0
Sold or booked
35%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Kundli Watch

VERTICA PHASE 2: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about VERTICA PHASE 2

Is VERTICA PHASE 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VERTICA PHASE 2 is registered as P52100034995 and its status is "Registered and active".

Where is VERTICA PHASE 2?

VERTICA PHASE 2 by V Realty is in Balewadi, Pune (pincode 411045), Maharashtra, and is registered on MahaRERA as P52100034995, per GharKundli's check of MahaRERA records.

When is possession of VERTICA PHASE 2 due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VERTICA PHASE 2 in Balewadi, Pune is 30 April 2029 — 37 months later than 31 March 2026, the date given at registration.

Does VERTICA PHASE 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of VERTICA PHASE 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is V Realty, which has 2 other projects registered on MahaRERA.

Other projects in pincode 411045

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.