NANDANVAN COLINA

by SAI SANKALP DEVELOPERS · Ambegaon Budruk, Pune

Registered on MahaRERA under P52100049350. Status: Lapsed (registration period ended). Its completion date has moved from August 2025 to June 2026, 10 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (June 2026) has passed.

GharKundli’s full report on NANDANVAN COLINA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100049350
Status
Lapsed (registration period ended)
Builder
SAI SANKALP DEVELOPERS
Location
Ambegaon Budruk, Pune · 411046
Project type
Residential / Group Housing
Registered on
7 Feb 2023
Completion date at registration
August 2025
Latest completion date
June 2026
Delay so far
10 months
Homes
72
Sold or booked
53%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Kundli Watch

NANDANVAN COLINA: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about NANDANVAN COLINA

Is NANDANVAN COLINA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDANVAN COLINA is registered as P52100049350 and its status is "Lapsed (registration period ended)".

Where is NANDANVAN COLINA?

NANDANVAN COLINA by SAI SANKALP DEVELOPERS is in Ambegaon Budruk, Pune (pincode 411046), Maharashtra, and is registered on MahaRERA as P52100049350, per GharKundli's check of MahaRERA records.

When is possession of NANDANVAN COLINA due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NANDANVAN COLINA in Ambegaon Budruk, Pune is 30 June 2026 — 10 months later than 31 August 2025, the date given at registration. That date has already passed.

Does NANDANVAN COLINA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of NANDANVAN COLINA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAI SANKALP DEVELOPERS, which has 2 other projects registered on MahaRERA.

Other projects in pincode 411046

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.