by GM RANAWAT VENTURES · Bibwewadi Munjeri, Pune

Registered on MahaRERA under P52100021608, and currently active. Its completion date has moved from December 2023 to April 2030, 76 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on AURA KOLLECTIVE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100021608
Status
Registered and active
Builder
GM RANAWAT VENTURES
Location
Bibwewadi Munjeri, Pune · 411037
Project type
Mixed
Registered on
15 Jul 2019
Completion date at registration
December 2023
Latest completion date
April 2030
Delay so far
76 months
Homes
29
Sold or booked
26%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

AURA KOLLECTIVE: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about AURA KOLLECTIVE

Is AURA KOLLECTIVE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AURA KOLLECTIVE is registered as P52100021608 and its status is "Registered and active".

Where is AURA KOLLECTIVE?

AURA KOLLECTIVE by GM RANAWAT VENTURES is in Bibwewadi Munjeri, Pune (pincode 411037), Maharashtra, and is registered on MahaRERA as P52100021608, per GharKundli's check of MahaRERA records.

When is possession of AURA KOLLECTIVE due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AURA KOLLECTIVE in Bibwewadi Munjeri, Pune is 30 April 2030 — 76 months later than 30 December 2023, the date given at registration.

Does AURA KOLLECTIVE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of AURA KOLLECTIVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GM RANAWAT VENTURES.

Other projects in pincode 411037

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.