GharKundli

Venkatesh Hill Side, Plot No. 2, Building 1

by VENKATESH ASSOCIATES · Dhayari, Pune

Registered on MahaRERA under P52100045700. Status: Completed. Its completion date has moved from May 2024 to November 2025, 18 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Venkatesh Hill Side, Plot No. 2, Building 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100045700
Status
Completed
Builder
VENKATESH ASSOCIATES
Location
Dhayari, Pune · 411041
Project type
Residential / Group Housing
Registered on
6 Jun 2022
Completion date at registration
May 2024
Latest completion date
November 2025
Delay so far
18 months
Homes
24
Sold or booked
83%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
14

Kundli Watch

Venkatesh Hill Side, Plot No. 2, Building 1: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Venkatesh Hill Side, Plot No. 2, Building 1

Is Venkatesh Hill Side, Plot No. 2, Building 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Venkatesh Hill Side, Plot No. 2, Building 1 is registered as P52100045700 and its status is "Completed".

Where is Venkatesh Hill Side, Plot No. 2, Building 1?

Venkatesh Hill Side, Plot No. 2, Building 1 by VENKATESH ASSOCIATES is in Dhayari, Pune (pincode 411041), Maharashtra, and is registered on MahaRERA as P52100045700, per GharKundli's check of MahaRERA records.

When is possession of Venkatesh Hill Side, Plot No. 2, Building 1 due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Venkatesh Hill Side, Plot No. 2, Building 1 in Dhayari, Pune is 30 November 2025 — 18 months later than 31 May 2024, the date given at registration.

Does Venkatesh Hill Side, Plot No. 2, Building 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of Venkatesh Hill Side, Plot No. 2, Building 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VENKATESH ASSOCIATES, which has 14 other projects registered on MahaRERA.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.