KOLEKAR APPARTMENT

by RAJAN DHANANJAY KOLEKAR · Baramati, Pune

Registered on MahaRERA under P52100080740, and currently active. Its completion date has moved from July 2027 to November 2027, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on KOLEKAR APPARTMENT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100080740
Status
Registered and active
Builder
RAJAN DHANANJAY KOLEKAR
Location
Baramati, Pune · 413102
Project type
Others
Registered on
1 Jul 2025
Completion date at registration
July 2027
Latest completion date
November 2027
Delay so far
4 months
Homes
15
Sold or booked
76%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Kundli Watch

KOLEKAR APPARTMENT: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about KOLEKAR APPARTMENT

Is KOLEKAR APPARTMENT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KOLEKAR APPARTMENT is registered as P52100080740 and its status is "Registered and active".

Where is KOLEKAR APPARTMENT?

KOLEKAR APPARTMENT by RAJAN DHANANJAY KOLEKAR is in Baramati, Pune (pincode 413102), Maharashtra, and is registered on MahaRERA as P52100080740, per GharKundli's check of MahaRERA records.

When is possession of KOLEKAR APPARTMENT due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KOLEKAR APPARTMENT in Baramati, Pune is 30 November 2027 — 4 months later than 31 July 2027, the date given at registration.

Does KOLEKAR APPARTMENT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of KOLEKAR APPARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAJAN DHANANJAY KOLEKAR, which has 1 other project registered on MahaRERA.

Other projects in pincode 413102

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.