Skip to content
GharKundli

ARCH DEVELOPERS

by ARCH DEVELOPERS · Vasai East, Palghar

Registered on MahaRERA under P99000029591, and currently active. Its completion date has moved from March 2023 to July 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on ARCH DEVELOPERS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000029591
Status
Registered and active
Builder
ARCH DEVELOPERS
Location
Vasai East, Palghar · 401208
Project type
Residential / Group Housing
Registered on
11 Jun 2021
Completion date at registration
March 2023
Latest completion date
July 2027
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
38%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Kundli Watch

ARCH DEVELOPERS: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about ARCH DEVELOPERS

Is ARCH DEVELOPERS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ARCH DEVELOPERS is registered as P99000029591 and its status is "Registered and active".

Where is ARCH DEVELOPERS?

ARCH DEVELOPERS by ARCH DEVELOPERS is in Vasai East, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000029591, per GharKundli's check of MahaRERA records.

When is possession of ARCH DEVELOPERS due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARCH DEVELOPERS in Vasai East, Palghar is 31 July 2027 — 48 months later than 31 March 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Does ARCH DEVELOPERS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of ARCH DEVELOPERS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARCH DEVELOPERS, which has 6 other projects registered on MahaRERA.

Other projects in pincode 401208

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.