AQSA BUILDING 2
by NEW STAR DEVELOPERS AQSA BUILDING 2 · Waliv Vasai, Palghar
Registered on MahaRERA under P99000030742, and currently active. Its completion date has moved from December 2023 to April 2027, 40 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on AQSA BUILDING 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000030742
- Status
- Registered and active
- Builder
- NEW STAR DEVELOPERS AQSA BUILDING 2
- Location
- Waliv Vasai, Palghar · 401208
- Project type
- Others
- Registered on
- 13 Sep 2021
- Completion date at registration
- December 2023
- Latest completion date
- April 2027
- Delay so far
- 40 months
- Homes
- 182
- Sold or booked
- 25%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
AQSA BUILDING 2: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about AQSA BUILDING 2
Is AQSA BUILDING 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AQSA BUILDING 2 is registered as P99000030742 and its status is "Registered and active".
Where is AQSA BUILDING 2?
AQSA BUILDING 2 by NEW STAR DEVELOPERS AQSA BUILDING 2 is in Waliv Vasai, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000030742, per GharKundli's check of MahaRERA records.
When is possession of AQSA BUILDING 2 due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AQSA BUILDING 2 in Waliv Vasai, Palghar is 30 April 2027 — 40 months later than 10 December 2023, the date given at registration.
Does AQSA BUILDING 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of AQSA BUILDING 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NEW STAR DEVELOPERS AQSA BUILDING 2.
Other projects in pincode 401208
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.