PRITHVI SAI YASH COMPLEX

by PRITHVI VAASTU DEVELOPERS · Chunabhatti, Palghar

Registered on MahaRERA under P99000032797, and currently active. Its completion date has moved from June 2024 to October 2027, 40 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on PRITHVI SAI YASH COMPLEX

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000032797
Status
Registered and active
Builder
PRITHVI VAASTU DEVELOPERS
Location
Chunabhatti, Palghar · 401407
Project type
Residential / Group Housing
Registered on
29 Jan 2022
Completion date at registration
June 2024
Latest completion date
October 2027
Delay so far
40 months
Homes
60
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

PRITHVI SAI YASH COMPLEX: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about PRITHVI SAI YASH COMPLEX

Is PRITHVI SAI YASH COMPLEX registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PRITHVI SAI YASH COMPLEX is registered as P99000032797 and its status is "Registered and active".

Where is PRITHVI SAI YASH COMPLEX?

PRITHVI SAI YASH COMPLEX by PRITHVI VAASTU DEVELOPERS is in Chunabhatti, Palghar (pincode 401407), Maharashtra, and is registered on MahaRERA as P99000032797, per GharKundli's check of MahaRERA records.

When is possession of PRITHVI SAI YASH COMPLEX due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PRITHVI SAI YASH COMPLEX in Chunabhatti, Palghar is 30 October 2027 — 40 months later than 30 June 2024, the date given at registration.

Does PRITHVI SAI YASH COMPLEX have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of PRITHVI SAI YASH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRITHVI VAASTU DEVELOPERS.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.