TRIPURA RESIDENCY

by AMRITA SANDIP BARMERA · Vasai, Palghar

Registered on MahaRERA under P99000047358, and currently active. Its completion date has moved from December 2024 to April 2028, 40 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on TRIPURA RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000047358
Status
Registered and active
Builder
AMRITA SANDIP BARMERA
Location
Vasai, Palghar · 401208
Project type
Residential / Group Housing
Registered on
27 Oct 2022
Completion date at registration
December 2024
Latest completion date
April 2028
Delay so far
40 months
Homes
33
Sold or booked
55%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

TRIPURA RESIDENCY: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about TRIPURA RESIDENCY

Is TRIPURA RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TRIPURA RESIDENCY is registered as P99000047358 and its status is "Registered and active".

Where is TRIPURA RESIDENCY?

TRIPURA RESIDENCY by AMRITA SANDIP BARMERA is in Vasai, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000047358, per GharKundli's check of MahaRERA records.

When is possession of TRIPURA RESIDENCY due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TRIPURA RESIDENCY in Vasai, Palghar is 30 April 2028 — 40 months later than 31 December 2024, the date given at registration.

Does TRIPURA RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of TRIPURA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AMRITA SANDIP BARMERA.

Other projects in pincode 401208

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.