Registered on MahaRERA under P99000080798, and currently active. Its completion date has moved from December 2030 to April 2031, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on KALPATRU AVENUE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000080798
Status
Registered and active
Builder
CROWNGOLDINFRA LLP
Location
Naigaon East., Palghar · 401208
Project type
Others
Registered on
10 Jul 2025
Completion date at registration
December 2030
Latest completion date
April 2031
Delay so far
4 months
Homes
203
Sold or booked
2%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

KALPATRU AVENUE: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about KALPATRU AVENUE

Is KALPATRU AVENUE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KALPATRU AVENUE is registered as P99000080798 and its status is "Registered and active".

Where is KALPATRU AVENUE?

KALPATRU AVENUE by CROWNGOLDINFRA LLP is in Naigaon East., Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000080798, per GharKundli's check of MahaRERA records.

When is possession of KALPATRU AVENUE due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KALPATRU AVENUE in Naigaon East., Palghar is 30 April 2031 — 4 months later than 31 December 2030, the date given at registration.

Does KALPATRU AVENUE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of KALPATRU AVENUE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CROWNGOLDINFRA LLP.