Hari Sanskruti Phase I
by KBC GLOBAL LIMITED · Deolali, NashikAlso near Chhatrapati Sambhajinagar Cantonment
Registered on MahaRERA under P51600001194. Status: Completed. Its completion date has moved from September 2020 to March 2026, 66 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Hari Sanskruti Phase I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600001194
- Status
- Completed
- Builder
- KBC GLOBAL LIMITED
- Location
- Deolali, Nashik · 422101
- Project type
- Residential / Group Housing
- Registered on
- 27 Jul 2017
- Completion date at registration
- September 2020
- Latest completion date
- March 2026
- Delay so far
- 66 months
- Homes
- 261
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 19
Kundli Watch
Hari Sanskruti Phase I: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Hari Sanskruti Phase I
Is Hari Sanskruti Phase I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Sanskruti Phase I is registered as P51600001194 and its status is "Completed".
Where is Hari Sanskruti Phase I?
Hari Sanskruti Phase I by KBC GLOBAL LIMITED is in Deolali, Nashik (pincode 422101), near Chhatrapati Sambhajinagar Cantonment, Maharashtra, and is registered on MahaRERA as P51600001194, per GharKundli's check of MahaRERA records.
When is possession of Hari Sanskruti Phase I due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hari Sanskruti Phase I in Deolali, Nashik is 31 March 2026 — 66 months later than 30 September 2020, the date given at registration.
Does Hari Sanskruti Phase I have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Hari Sanskruti Phase I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KBC GLOBAL LIMITED, which has 19 other projects registered on MahaRERA.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.