How to check the construction status of a project on MahaRERA

Updated 13 November 2026 · Based on the RERA Act 2016 and MahaRERA’s rules · General information, not legal advice

Short answer

Builders must update their project on MahaRERA every quarter, including the status of construction (Section 11(1) of the RERA Act). Search the project on MahaRERA, open View Details and read the building-wise progress the builder filed: floors and slabs done, and how much of each work item is complete. Compare it with what you see at the site and with the completion date. GharKundli's project pages show the floors and buildings the builder filed, so you can check quickly below.

Check a project quickly

Type the project name to see its completion date, then open its full MahaRERA record for the buildings and floors the builder filed.

On MahaRERA, step by step

  1. Open MahaRERA's Search Project page and search by project name or registration number.
  2. Pick your wing's registration and open "View Details" (type the code shown).
  3. Look at the building details: number of floors, and the progress the builder reported for each building and work item.
  4. Note when the project was last updated ("Last Modified" in the search result). A project that hasn't been updated for many months is a warning.

How to read what you find

  • Compare progress with time left. If half the building is still to be built and the completion date is a few months away, expect a delay.
  • Check that floors match the approval. More floors filed than at registration usually means a revised plan; ask what changed for your flat.
  • Visit the site and take dated photos. The quarterly filing is the builder's own statement; the site is the truth.
  • No update for a long time: MahaRERA has red-flagged and taken action against projects that didn't file their quarterly updates.

If construction has stopped

Write to the builder for a revised timeline, get in touch with the other buyers, and know your rights under Section 18. The guide on a builder who has stopped construction explains each step.

Ready letters to send the builder

Copy, fill in the [brackets], and send by email or registered post. Keep a copy.

Letter asking the builder for the revised possession date
To,
[Builder's company name]
[Builder's address]

Date: [today's date]

Subject: Revised possession date of Flat [flat no.], [wing/building], [project name] (MahaRERA [registration no.])

Dear Sir/Madam,

I booked the above flat under a registered agreement for sale dated [agreement date] (registration no. [document no.]). The agreement gives the date of possession as [possession date in the agreement].

Please confirm in writing, within 15 days:
1. The date on which you will offer possession of my flat, with the occupancy certificate.
2. The present stage of construction of my building.
3. The reason for any delay beyond the date in my agreement.

Please note that my rights under Section 18 of the Real Estate (Regulation and Development) Act, 2016 run from the date of possession in my agreement.

Yours faithfully,
[Your name]
[Phone] · [Email]

How GharKundli helps

  • Check the project’s record — a GharKundli report pulls the project’s MahaRERA filings into one place: registration status, completion dates, complaints, construction progress and the builder’s other projects.
  • Act with the other buyers — join your project’s verified owners on Kundli Watch. If something serious is confirmed, we connect the owners who agreed to act together; your number is shared only with owners who also agreed.

Common questions

How often must the builder update construction status on MahaRERA?

Every quarter. Section 11(1) of the RERA Act requires the promoter to update the project's page with the bookings, approvals and status of the project every quarter.

Is the construction status on MahaRERA certified?

The progress filings are the builder's own statements, supported by the certificates of the project's architect, engineer and chartered accountant that MahaRERA requires for withdrawals from the project's bank account. Still check the site yourself.

The project shows no update for a year. What does that mean?

The builder has not filed what the law requires. It can mean a slow or stalled project. Ask the builder in writing, and check the project's complaints and MahaRERA orders before paying more.

Still have a question?

Ask us on WhatsApp. We answer from the project’s MahaRERA record, and the questions buyers ask most are added to this page.

Ask on WhatsApp

Also asked as

  • Construction status kaise check kare?
  • Current construction status of my project
  • How to read the quarterly progress report on MahaRERA
  • Is my builder's project on track?

Sources

This page explains the law in general terms. Every case is different — for a complaint or any legal step, speak to a lawyer experienced in RERA matters. GharKundli is not a law firm.