Possession due in 2027 · Ahmednagar
According to GharKundli's check of MahaRERA records, 2 housing projects in Ahmednagar have a MahaRERA completion date in 2027, out of 15 Ahmednagar projects GharKundli has read in detail so far.
The date is the latest completion date the builder has filed on MahaRERA, including MahaRERA’s automatic 4-month extension of August 2026 where it applies. “First promised” is the date given at registration. Completed projects are not listed. Open a project for its full MahaRERA record.
| Project | Where | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| SKY HEIGHT PRANALI INFRASTRUCTURE | Sawedi | 31 Jan 2027 | 31 Dec 2024 | 0 |
| Dhadiwal Raisoni Plaza DHADIWAL RAISONI ASSOCIATES | Rahata Ahmednagar | 30 Apr 2027 | 31 Dec 2025 | 0 |
Other years in Ahmednagar: 2026 (3) · 2028 (7) · 2029 (5) · 2030 (7) · 2031 (6)
Source: GharKundli’s check of MahaRERA records. More projects appear as GharKundli reads them.