PANVELKAR UTSAV - PHASE 2

by Sai Swarg Enterprises · Valivali Village, Thane

Registered on MahaRERA under P51700022593. Status: Lapsed (registration period ended). Its completion date has moved from December 2023 to December 2025, 24 months later.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2025) has passed.

GharKundli’s full report on PANVELKAR UTSAV - PHASE 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700022593
Status
Lapsed (registration period ended)
Builder
Sai Swarg Enterprises
Location
Valivali Village, Thane · 421503
Project type
Residential / Group Housing
Registered on
9 Oct 2019
Completion date at registration
December 2023
Latest completion date
December 2025
Delay so far
24 months
Homes
202
Sold or booked
0%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Kundli Watch

PANVELKAR UTSAV - PHASE 2: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about PANVELKAR UTSAV - PHASE 2

Is PANVELKAR UTSAV - PHASE 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PANVELKAR UTSAV - PHASE 2 is registered as P51700022593 and its status is "Lapsed (registration period ended)".

Where is PANVELKAR UTSAV - PHASE 2?

PANVELKAR UTSAV - PHASE 2 by Sai Swarg Enterprises is in Valivali Village, Thane (pincode 421503), Maharashtra, and is registered on MahaRERA as P51700022593, per GharKundli's check of MahaRERA records.

When is possession of PANVELKAR UTSAV - PHASE 2 due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PANVELKAR UTSAV - PHASE 2 in Valivali Village, Thane is 31 December 2025 — 24 months later than 30 December 2023, the date given at registration. That date has already passed.

Does PANVELKAR UTSAV - PHASE 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in PANVELKAR UTSAV - PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), PANVELKAR UTSAV - PHASE 2 has 202 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.

When was PANVELKAR UTSAV - PHASE 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PANVELKAR UTSAV - PHASE 2 was registered on MahaRERA on 9 October 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on PANVELKAR UTSAV - PHASE 2?

No court cases are listed for PANVELKAR UTSAV - PHASE 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PANVELKAR UTSAV - PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sai Swarg Enterprises, which has 1 other project registered on MahaRERA.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.