by Girija Developers · Kherdi, Ratnagiri

Registered on MahaRERA under P52800015860, and currently active. Its completion date has moved from December 2023 to April 2031: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Girija Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800015860
Status
Registered and active
Builder
Girija Developers
Location
Kherdi, Ratnagiri · 415604
Project type
Residential / Group Housing
Registered on
28 Mar 2018
Completion date at registration
December 2023
Latest completion date
April 2031
Delay so far
84 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
80
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Kundli Watch

Girija Residency: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Girija Residency

Is Girija Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Girija Residency is registered as P52800015860 and its status is "Registered and active".

Where is Girija Residency?

Girija Residency by Girija Developers is in Kherdi, Ratnagiri (pincode 415604), Maharashtra, and is registered on MahaRERA as P52800015860, per GharKundli's check of MahaRERA records.

When is possession of Girija Residency due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Girija Residency in Kherdi, Ratnagiri is 30 April 2031 — 84 months later than 25 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Does Girija Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

How many homes are in Girija Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Girija Residency has 80 homes in 4 towers registered on MahaRERA.

When was Girija Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Girija Residency was registered on MahaRERA on 28 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Girija Residency?

No court cases are listed for Girija Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Girija Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Girija Developers, which has 1 other project registered on MahaRERA.

Other projects in pincode 415604

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.