AYODHYA PARK
by PRAMAY ENTERPRISES · Lashkarwadi, Ratnagiri
Registered on MahaRERA under P52800049259. Status: Completed. Its completion date has moved from May 2025 to December 2026, 19 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on AYODHYA PARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800049259
- Status
- Completed
- Builder
- PRAMAY ENTERPRISES
- Location
- Lashkarwadi, Ratnagiri · 415712
- Project type
- Residential / Group Housing
- Registered on
- 3 Feb 2023
- Completion date at registration
- May 2025
- Latest completion date
- December 2026
- Delay so far
- 19 months
- Homes
- 12
- Sold or booked
- 88%
- Towers
- 6
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Kundli Watch
AYODHYA PARK: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about AYODHYA PARK
Is AYODHYA PARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AYODHYA PARK is registered as P52800049259 and its status is "Completed".
Where is AYODHYA PARK?
AYODHYA PARK by PRAMAY ENTERPRISES is in Lashkarwadi, Ratnagiri (pincode 415712), Maharashtra, and is registered on MahaRERA as P52800049259, per GharKundli's check of MahaRERA records.
When is possession of AYODHYA PARK due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AYODHYA PARK in Lashkarwadi, Ratnagiri is 31 December 2026 — 19 months later than 31 May 2025, the date given at registration.
Does AYODHYA PARK have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
How many homes are in AYODHYA PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), AYODHYA PARK has 12 homes in 6 towers registered on MahaRERA, and 88% of them are sold or booked.
When was AYODHYA PARK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AYODHYA PARK was registered on MahaRERA on 3 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on AYODHYA PARK?
No court cases are listed for AYODHYA PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AYODHYA PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRAMAY ENTERPRISES, which has 1 other project registered on MahaRERA.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.