Skip to content
GharKundli

Siddhidata Park

by ABHIJIT PRAKASH JAITAPKAR · Oros, Sindhudurg

Registered on MahaRERA under P52900010635. Status: Completed. Its completion date has moved from September 2019 to March 2022, 30 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on Siddhidata Park

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900010635
Status
Completed
Builder
ABHIJIT PRAKASH JAITAPKAR
Location
Oros, Sindhudurg · 416812
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
September 2019
Latest completion date
March 2022
Delay so far
30 months
Homes
36
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

Siddhidata Park: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about Siddhidata Park

Is Siddhidata Park registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhidata Park is registered as P52900010635 and its status is "Completed".

Where is Siddhidata Park?

Siddhidata Park by ABHIJIT PRAKASH JAITAPKAR is in Oros, Sindhudurg (pincode 416812), Maharashtra, and is registered on MahaRERA as P52900010635, per GharKundli's check of MahaRERA records.

When is possession of Siddhidata Park due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Siddhidata Park in Oros, Sindhudurg is 8 March 2022 — 30 months later than 30 September 2019, the date given at registration.

Does Siddhidata Park have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

How many homes are in Siddhidata Park?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhidata Park has 36 homes in 3 towers registered on MahaRERA.

When was Siddhidata Park registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhidata Park was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Siddhidata Park?

No court cases are listed for Siddhidata Park on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Siddhidata Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ABHIJIT PRAKASH JAITAPKAR.

Other projects in pincode 416812