Registered on MahaRERA under P51700028899. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on PURVA PRIME

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700028899
Status
Completed
Builder
TRIMURTI CONSTRUCTIONS
Location
Dombivli, Thane · 421202
Project type
Residential / Group Housing
Registered on
7 Apr 2021
Completion date at registration
September 2026
Latest completion date
September 2026
Homes
27
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Kundli Watch

PURVA PRIME: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PURVA PRIME

Is PURVA PRIME registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PURVA PRIME is registered as P51700028899 and its status is "Completed".

Where is PURVA PRIME?

PURVA PRIME by TRIMURTI CONSTRUCTIONS is in Dombivli, Thane (pincode 421202), Maharashtra, and is registered on MahaRERA as P51700028899, per GharKundli's check of MahaRERA records.

When is possession of PURVA PRIME due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PURVA PRIME in Dombivli, Thane is 30 September 2026.

Does PURVA PRIME have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in PURVA PRIME?

According to GharKundli's check of MahaRERA records (updated November 2026), PURVA PRIME has 27 homes in 1 tower registered on MahaRERA.

When was PURVA PRIME registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PURVA PRIME was registered on MahaRERA on 7 April 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on PURVA PRIME?

No court cases are listed for PURVA PRIME on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PURVA PRIME?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is TRIMURTI CONSTRUCTIONS, which has 1 other project registered on MahaRERA.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.