KRUSHNA GARDEN

by LOKHANDE JAGDALE ASSOCIATE · Ramkrishnanagar, SataraAlso near Sangamnagar Satara

Registered on MahaRERA under P52700013667, and currently active. Its completion date has moved from June 2021 to April 2029: 90 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on KRUSHNA GARDEN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52700013667
Status
Registered and active
Builder
LOKHANDE JAGDALE ASSOCIATE
Location
Ramkrishnanagar, Satara · 415001
Project type
Residential / Group Housing
Registered on
23 Oct 2017
Completion date at registration
June 2021
Latest completion date
April 2029
Delay so far
90 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
140
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

KRUSHNA GARDEN: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about KRUSHNA GARDEN

Is KRUSHNA GARDEN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNA GARDEN is registered as P52700013667 and its status is "Registered and active".

Where is KRUSHNA GARDEN?

KRUSHNA GARDEN by LOKHANDE JAGDALE ASSOCIATE is in Ramkrishnanagar, Satara (pincode 415001), near Sangamnagar Satara, Maharashtra, and is registered on MahaRERA as P52700013667, per GharKundli's check of MahaRERA records.

When is possession of KRUSHNA GARDEN due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KRUSHNA GARDEN in Ramkrishnanagar, Satara is 30 April 2029 — 90 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Does KRUSHNA GARDEN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

How many homes are in KRUSHNA GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNA GARDEN has 140 homes in 4 towers registered on MahaRERA.

When was KRUSHNA GARDEN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNA GARDEN was registered on MahaRERA on 23 October 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KRUSHNA GARDEN?

No court cases are listed for KRUSHNA GARDEN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of KRUSHNA GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LOKHANDE JAGDALE ASSOCIATE.

All projects with possession due in 2029 in Satara →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.