OPULENCE
by SIDHIVINAYAK CONSTRUCTIONS · Chembur, MumbaiAlso near T F Deonar, Anushakti Nagar
Registered on MahaRERA under P51800002068. Status: Completed. Its completion date has moved from December 2018 to December 2020, 24 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
GharKundli’s full report on OPULENCE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800002068
- Status
- Completed
- Builder
- SIDHIVINAYAK CONSTRUCTIONS
- Location
- Chembur, Mumbai · 400088
- Project type
- Residential / Group Housing
- Registered on
- 31 Jul 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2020
- Delay so far
- 24 months
- Homes
- 68
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Kundli Watch
OPULENCE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about OPULENCE
Is OPULENCE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OPULENCE is registered as P51800002068 and its status is "Completed".
Where is OPULENCE?
OPULENCE by SIDHIVINAYAK CONSTRUCTIONS is in Chembur, Mumbai (pincode 400088), near T F Deonar, Anushakti Nagar, Maharashtra, and is registered on MahaRERA as P51800002068, per GharKundli's check of MahaRERA records.
When is possession of OPULENCE due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for OPULENCE in Chembur, Mumbai is 30 December 2020 — 24 months later than 31 December 2018, the date given at registration.
Does OPULENCE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in OPULENCE?
According to GharKundli's check of MahaRERA records (updated November 2026), OPULENCE has 68 homes in 1 tower registered on MahaRERA.
When was OPULENCE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OPULENCE was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on OPULENCE?
No court cases are listed for OPULENCE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of OPULENCE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SIDHIVINAYAK CONSTRUCTIONS, which has 5 other projects registered on MahaRERA.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.