Skip to content
GharKundli

SHALOM ARCADE

by JACOB GEORGE · Kopar Khairane, Raigarh

Registered on MahaRERA under P52000009209. Status: Completed. Its completion date has moved from March 2020 to March 2022, 24 months later.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on SHALOM ARCADE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000009209
Status
Completed
Builder
JACOB GEORGE
Location
Kopar Khairane, Raigarh · 400702
Project type
Others
Registered on
22 Aug 2017
Completion date at registration
March 2020
Latest completion date
March 2022
Delay so far
24 months
Homes
28
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Kundli Watch

SHALOM ARCADE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHALOM ARCADE

Is SHALOM ARCADE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALOM ARCADE is registered as P52000009209 and its status is "Completed".

Where is SHALOM ARCADE?

SHALOM ARCADE by JACOB GEORGE is in Kopar Khairane, Raigarh (pincode 400702), Maharashtra, and is registered on MahaRERA as P52000009209, per GharKundli's check of MahaRERA records.

When is possession of SHALOM ARCADE due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHALOM ARCADE in Kopar Khairane, Raigarh is 30 March 2022 — 24 months later than 31 March 2020, the date given at registration.

Does SHALOM ARCADE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in SHALOM ARCADE?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALOM ARCADE has 28 homes in 1 tower registered on MahaRERA.

When was SHALOM ARCADE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALOM ARCADE was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHALOM ARCADE?

No court cases are listed for SHALOM ARCADE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHALOM ARCADE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is JACOB GEORGE, which has 1 other project registered on MahaRERA.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.