DATTA VIHAR
by MAITREE BUILDERS · Palaspe, Raigarh
Registered on MahaRERA under P52000013719. Status: Completed. Its completion date has moved from March 2021 to May 2024, 38 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on DATTA VIHAR
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000013719
- Status
- Completed
- Builder
- MAITREE BUILDERS
- Location
- Palaspe, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 23 Oct 2017
- Completion date at registration
- March 2021
- Latest completion date
- May 2024
- Delay so far
- 38 months
- Homes
- 48
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
DATTA VIHAR: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about DATTA VIHAR
Is DATTA VIHAR registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DATTA VIHAR is registered as P52000013719 and its status is "Completed".
Where is DATTA VIHAR?
DATTA VIHAR by MAITREE BUILDERS is in Palaspe, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000013719, per GharKundli's check of MahaRERA records.
When is possession of DATTA VIHAR due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DATTA VIHAR in Palaspe, Raigarh is 3 May 2024 — 38 months later than 30 March 2021, the date given at registration.
Does DATTA VIHAR have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of DATTA VIHAR?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAITREE BUILDERS.
Other projects in pincode 410206
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.