Wise City RZ-01 Plotted Development - Phase 3
by Wadhwa Construction and infrastructure Private Limited · Wadhwa Wise City, Raigarh 410206
What’s in the report? →Possession date of Wise City RZ-01 Plotted Development - Phase 3 (MahaRERA P52000052569): 30 April 2028, moved from 31 December 2026 (16 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000052569, and currently active.
Source: MahaRERA website — records for P52000052569, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Wise City RZ-01 Plotted Development - Phase 3?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Wise City RZ-01 Plotted Development - Phase 3 has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
Extended at the builder's request
30 April 2028
Extended at the builder's request (MahaRERA application EA09092622493)
Reason the builder gave MahaRERA:
“We are requesting an extension of the project completion date 30th April 2028 due to circumstances beyond our control. The delay has been caused primarily due to ongoing issues with the local villagers, which have obstructed construction ac…” Read the full reason
“We are requesting an extension of the project completion date 30th April 2028 due to circumstances beyond our control. The delay has been caused primarily due to ongoing issues with the local villagers, which have obstructed construction activities on certain plots located along the internal access road of the Plotted development. The local villagers are presently not permitting us to carry out the required construction and development work in these areas. Despite our continuous efforts to resolve the matter amicably, the issue remains unresolved. As a result, the construction and developme…”
Source: Wise City RZ-01 Plotted Development - Phase 3’s extension records on MahaRERA (P52000052569), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Wise City RZ-01 Plotted Development - Phase 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Wise City RZ-01 Plotted Development - Phase 1P52000052619 · possession 30 Apr 2028
- Wise City RZ-01 Plotted Development - Phase 2P52000052572 · possession 30 Apr 2028
- MahaRERA registration
- P52000052569
- Status
- Registered and active
- Builder
- Wadhwa Construction and infrastructure Private Limited
- Location
- Wadhwa Wise City, Raigarh · 410206
- Project type
- Plotted
- Registered on
- 11 Sep 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2028
- Delay so far
- 16 months
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 27
Wise City RZ-01 Plotted Development - Phase 3: buildings, flats and land, as filed on MahaRERA
- Land: 40,294 sq m (about 10.0 acres) · recreational space 4,271 sq m
- Land, as filed: 82/4, 82/5, 82/6, 82/7, 82/8, 82/10, 82/3, 82/13, 84/3 (Pt), 84/4 (Pt), 86/1, 86/2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Wise City RZ-01 Plotted Development - Phase 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Wise City RZ-01 Plotted Development - Phase 3: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Wise City RZ-01 Plotted Development - Phase 3
What is the possession date of Wise City RZ-01 Plotted Development - Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Wise City RZ-01 Plotted Development - Phase 3 in Wadhwa Wise City, Raigarh is 30 April 2028 — 16 months later than 31 December 2026, the date given at registration.
The date has already moved 16 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Wise City RZ-01 Plotted Development - Phase 3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Wise City RZ-01 Plotted Development - Phase 3's builder has filed on MahaRERA, the official one, is 30 April 2028, already 16 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Wise City RZ-01 Plotted Development - Phase 3 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Wise City RZ-01 Plotted Development - Phase 3's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2027; to 30 April 2028, giving the reason "We are requesting an extension of the project completion date 30th April 2028 due to circumstances beyond our control. The delay has been caused primarily due to ongoing issues with the local villagers, which have obstructed construction activities on certain plots located along the internal access road of the Plotted development. The local villagers are presently not permitting us to carry out the required construction and development work in these areas. Despite our continuous efforts to resolve the matter amicably, the issue remains unresolved. As a result, the construction and developme…".
What is the RERA number of Wise City RZ-01 Plotted Development - Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Wise City RZ-01 Plotted Development - Phase 3 in Wadhwa Wise City, Raigarh is P52000052569.
Is Wise City RZ-01 Plotted Development - Phase 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Wise City RZ-01 Plotted Development - Phase 3 is registered as P52000052569 and its status is "Registered and active".
What is the current construction status of Wise City RZ-01 Plotted Development - Phase 3? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Wise City RZ-01 Plotted Development - Phase 3's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does Wise City RZ-01 Plotted Development - Phase 3 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Wise City RZ-01 Plotted Development - Phase 3 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Wise City RZ-01 Plotted Development - Phase 3 is registered on MahaRERA as P52000052569, its completion date has moved 16 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Wise City RZ-01 Plotted Development - Phase 3?
Wise City RZ-01 Plotted Development - Phase 3 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Wise City RZ-01 Plotted Development - Phase 3?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Wise City RZ-01 Plotted Development - Phase 3: gharkundli.com/tools/property-cost-calculator
Has Wise City RZ-01 Plotted Development - Phase 3 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Wise City RZ-01 Plotted Development - Phase 3 is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Wise City RZ-01 Plotted Development - Phase 3 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Wise City RZ-01 Plotted Development - Phase 3 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Wise City RZ-01 Plotted Development - Phase 3 have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Wise City RZ-01 Plotted Development - Phase 1 (P52000052619, possession 30 Apr 2028); Wise City RZ-01 Plotted Development - Phase 2 (P52000052572, possession 30 Apr 2028). Check that your agreement names the registration of your own wing.
How can I get updates if Wise City RZ-01 Plotted Development - Phase 3's possession date changes?
The latest dates are on Wise City RZ-01 Plotted Development - Phase 3's MahaRERA page (P52000052569). GharKundli's Kundli Watch sends a free WhatsApp update on Wise City RZ-01 Plotted Development - Phase 3 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of Wise City RZ-01 Plotted Development - Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), Wise City RZ-01 Plotted Development - Phase 3 stands on 40,294 sq m of land (about 10.0 acres) and 4,271 sq m of recreational open space.
What are the reviews of Wise City RZ-01 Plotted Development - Phase 3?
Google Maps has reviews of Wise City RZ-01 Plotted Development - Phase 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Wise City RZ-01 Plotted Development - Phase 3?
Wise City RZ-01 Plotted Development - Phase 3 by Wadhwa Construction and infrastructure Private Limited is in Wadhwa Wise City, Raigarh, pincode 410206, Maharashtra, and is registered on MahaRERA as P52000052569, per GharKundli's check of MahaRERA records. Its land is filed as 82/4, 82/5, 82/6, 82/7, 82/8, 82/10, 82/3, 82/13, 84/3 (Pt), 84/4 (Pt), 86/1, 86/2. GharKundli lists all 2,664 MahaRERA projects in Panvel (410206).
When was Wise City RZ-01 Plotted Development - Phase 3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Wise City RZ-01 Plotted Development - Phase 3 was registered on MahaRERA on 11 September 2023. GharKundli did not find a title report on the land on file there.
Does Wise City RZ-01 Plotted Development - Phase 3 have any legal issues or court cases?
No court cases are listed for Wise City RZ-01 Plotted Development - Phase 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Wise City RZ-01 Plotted Development - Phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Wadhwa Construction and infrastructure Private Limited, which has 27 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Wise City RZ-01 Plotted Development - Phase 3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Raigad →
Other projects in Panvel (410206)
- Wise City RZ-01 Plotted Development - Phase 2
- Wise City RZ-01 Plotted Development - Phase 1
- wise city, south Block, Phase I, Plot RZ8 Building 1 wing A3
- Wise City RZ8 Wing D5
- Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F4
- Wise City, South Block Phase I, Plot RZ8, Building 3 Wing C3
- Wise City, South Block Phase I, Plot RZ8 Building 2 Wing B3
- Wise City, South Block Phase I, Plot Rz8 Building 3 Wing C1
Other projects by Wadhwa Construction and infrastructure Private Limited
- Wise City RZ-01 Plotted Development - Phase 2
- Wise City RZ-01 Plotted Development - Phase 1
- wise city, south Block, Phase I, Plot RZ8 Building 1 wing A3
- Wise City RZ8 Wing D5
- Wise City, South Block Phase I, Plot RZ8, Building 5 Wing D4
- Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F4
- Wise City, South Block Phase I, Plot RZ8, Building 3 Wing C3
- Wise City, South Block Phase I, Plot RZ8 Building 2 Wing B3
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.