GharKundli research · November 2026
What builders tell MahaRERA when they’re late
Published 14 November 2026 · Data: MahaRERA public records · Free to use with credit (CC BY 4.0)
Key findings
- In 9,619 of 33,647 projects (29%), about 2 in 7, the builder applied to MahaRERA for more time at least once: 14,973 extension applications in all.
- A builder’s extensions pushed the completion date by a median of 19 months; for a quarter of these projects, by 3 years or more.
- 1,287 projects were extended 3 or more times, and 172 were extended 5 or more times.
- The most common reason is approvals and permissions (48% of applications), then labour and material shortages (28%) and COVID-19 (24%).
- 620 applications still blame COVID-19 for completion dates in 2026, 2027 and 2028, six years after the first lockdown.
- 1 in 3 Mumbai projects needed more time (38% in Mumbai city, 33% in Mumbai Suburban), against 25% in Thane and 22% in Raigad.

The reasons, in full
Share of the 14,968 applications that give a reason. One application often gives several, so the shares add up to more than 100%.
| Reason given | Applications | Share |
|---|---|---|
| Approvals and permissions (CC, OC, NOCs, plans) | 7,201 | 48% |
| Labour and material shortages | 4,141 | 28% |
| COVID-19 / lockdown | 3,565 | 24% |
| Funds and finance | 2,341 | 16% |
| Sales slowdown / market | 1,555 | 10% |
| Government or policy changes | 1,241 | 8% |
| Tenants, society and redevelopment | 862 | 6% |
| TDR / FSI / premium | 774 | 5% |
| Court cases and disputes | 693 | 5% |
| Monsoon / weather | 486 | 3% |
| Land and title | 185 | 1% |
| Other / not stated clearly | 2,620 | 18% |

By district
Districts with 300 or more projects read in detail.
| District | Projects read | Builder asked for more time | Share |
|---|---|---|---|
| Mumbai (city) | 1,187 | 449 | 37.8% |
| Palghar | 1,580 | 564 | 35.7% |
| Pune | 6,541 | 2,265 | 34.6% |
| Mumbai Suburban | 6,342 | 2,077 | 32.7% |
| Ratnagiri | 374 | 110 | 29.4% |
| Satara | 420 | 115 | 27.4% |
| Aurangabad | 450 | 119 | 26.4% |
| Thane | 6,714 | 1,670 | 24.9% |
| Kolhapur | 358 | 83 | 23.2% |
| Raigad | 5,376 | 1,192 | 22.2% |
| Nashik | 1,371 | 283 | 20.6% |
| Nagpur | 1,260 | 244 | 19.4% |
What it means for a buyer
An extension on MahaRERA doesn’t change the possession date in your agreement for sale: your right to interest for the delay still runs from that date. Before you book, look at how often the project’s date has already moved, and the reasons the builder gave. Type a project name to see its completion date and how far it has moved:
Possession delayed? Work out the interest the builder owes →Our earlier study: half of all MahaRERA complaints come from 427 projects →
How we counted
- Projects: the 33,647 MahaRERA projects GharKundli has read in detail (of 55,399 registered), each from its latest reading (October and November 2026).
- Extensions: the extension records on each project’s MahaRERA page. We counted only extensions the builder applied for (application numbers starting EXT or EA): 14,973. MahaRERA’s automatic extensions for all eligible projects (the COVID-era ones, and the 2026 order) are left out: they are not the builder’s request.
- Reasons: the reason written in each application, sorted into kinds by keywords. One application often gives several reasons; 2,620 gave none we could sort clearly.
- Months added: from the completion date at registration to the latest date the builder asked for.
- District: from each project’s pincode, using India Post’s pincode directory.
Caveats
- GharKundli read recently active projects and Mumbai, Thane and Raigad first, so the 33,647 lean towards active projects.
- Sorting reasons by keywords is approximate; the shares show which reasons are common, not exact counts.
- MahaRERA grants extensions under the RERA Act; an extension is not proof of wrongdoing.
Use and cite
Free to use under CC BY 4.0. Please credit “GharKundli (gharkundli.com)” and link to this page. Journalists can ask for more detail by district or year.
GharKundli (2026). What builders tell MahaRERA when they’re late: extension applications and reasons, November 2026. gharkundli.com/research/maharera-delay-reasons