What builders tell MahaRERA when they’re late

Published 14 November 2026 · Data: MahaRERA public records · Free to use with credit (CC BY 4.0)

Key findings

  • In 9,619 of 33,647 projects (29%), about 2 in 7, the builder applied to MahaRERA for more time at least once: 14,973 extension applications in all.
  • A builder’s extensions pushed the completion date by a median of 19 months; for a quarter of these projects, by 3 years or more.
  • 1,287 projects were extended 3 or more times, and 172 were extended 5 or more times.
  • The most common reason is approvals and permissions (48% of applications), then labour and material shortages (28%) and COVID-19 (24%).
  • 620 applications still blame COVID-19 for completion dates in 2026, 2027 and 2028, six years after the first lockdown.
  • 1 in 3 Mumbai projects needed more time (38% in Mumbai city, 33% in Mumbai Suburban), against 25% in Thane and 22% in Raigad.
Bar chart: reasons builders gave MahaRERA in 14,968 extension applications. Approvals and permissions 48%, labour and material shortages 28%, COVID-19 24%, funds and finance 16%, sales slowdown 10%, government or policy changes 8%, tenants and redevelopment 6%, TDR/FSI/premium 5%, court cases 5%, monsoon 3%.
Free to publish with the credit “GharKundli analysis of MahaRERA data (gharkundli.com)”. Download the reasons chart (PNG)

The reasons, in full

Share of the 14,968 applications that give a reason. One application often gives several, so the shares add up to more than 100%.

Reason givenApplicationsShare
Approvals and permissions (CC, OC, NOCs, plans)7,20148%
Labour and material shortages4,14128%
COVID-19 / lockdown3,56524%
Funds and finance2,34116%
Sales slowdown / market1,55510%
Government or policy changes1,2418%
Tenants, society and redevelopment8626%
TDR / FSI / premium7745%
Court cases and disputes6935%
Monsoon / weather4863%
Land and title1851%
Other / not stated clearly2,62018%
Download the reasons (CSV)
Bar chart: share of projects whose builder applied to MahaRERA for an extension, by district. Mumbai city 38%, Palghar 36%, Pune 35%, Mumbai Suburban 33%, Ratnagiri 29%, Satara 27%, Aurangabad 26%, Thane 25%, Kolhapur 23%, Raigad 22%, Nashik 21%, Nagpur 19%.
Free to publish with the credit “GharKundli analysis of MahaRERA data (gharkundli.com)”. Download the district chart (PNG)

By district

Districts with 300 or more projects read in detail.

DistrictProjects readBuilder asked for more timeShare
Mumbai (city)1,18744937.8%
Palghar1,58056435.7%
Pune6,5412,26534.6%
Mumbai Suburban6,3422,07732.7%
Ratnagiri37411029.4%
Satara42011527.4%
Aurangabad45011926.4%
Thane6,7141,67024.9%
Kolhapur3588323.2%
Raigad5,3761,19222.2%
Nashik1,37128320.6%
Nagpur1,26024419.4%
Download the district table (CSV)

What it means for a buyer

An extension on MahaRERA doesn’t change the possession date in your agreement for sale: your right to interest for the delay still runs from that date. Before you book, look at how often the project’s date has already moved, and the reasons the builder gave. Type a project name to see its completion date and how far it has moved:

Possession delayed? Work out the interest the builder owes →Our earlier study: half of all MahaRERA complaints come from 427 projects →

How we counted

  1. Projects: the 33,647 MahaRERA projects GharKundli has read in detail (of 55,399 registered), each from its latest reading (October and November 2026).
  2. Extensions: the extension records on each project’s MahaRERA page. We counted only extensions the builder applied for (application numbers starting EXT or EA): 14,973. MahaRERA’s automatic extensions for all eligible projects (the COVID-era ones, and the 2026 order) are left out: they are not the builder’s request.
  3. Reasons: the reason written in each application, sorted into kinds by keywords. One application often gives several reasons; 2,620 gave none we could sort clearly.
  4. Months added: from the completion date at registration to the latest date the builder asked for.
  5. District: from each project’s pincode, using India Post’s pincode directory.

Caveats

  • GharKundli read recently active projects and Mumbai, Thane and Raigad first, so the 33,647 lean towards active projects.
  • Sorting reasons by keywords is approximate; the shares show which reasons are common, not exact counts.
  • MahaRERA grants extensions under the RERA Act; an extension is not proof of wrongdoing.

Use and cite

Free to use under CC BY 4.0. Please credit “GharKundli (gharkundli.com)” and link to this page. Journalists can ask for more detail by district or year.

GharKundli (2026). What builders tell MahaRERA when they’re late: extension applications and reasons, November 2026. gharkundli.com/research/maharera-delay-reasons