NESTOR
by KALPANA STRUCT-CON INFRA LLP · Dronagiri, Raigarh
Registered on MahaRERA under P52000014902. Status: Completed. Its completion date has moved from December 2022 to March 2025, 27 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on NESTOR
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000014902
- Status
- Completed
- Builder
- KALPANA STRUCT-CON INFRA LLP
- Location
- Dronagiri, Raigarh · 400702
- Project type
- Others
- Registered on
- 11 Jan 2018
- Completion date at registration
- December 2022
- Latest completion date
- March 2025
- Delay so far
- 27 months
- Homes
- 128
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
NESTOR: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about NESTOR
Is NESTOR registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NESTOR is registered as P52000014902 and its status is "Completed".
Where is NESTOR?
NESTOR by KALPANA STRUCT-CON INFRA LLP is in Dronagiri, Raigarh (pincode 400702), Maharashtra, and is registered on MahaRERA as P52000014902, per GharKundli's check of MahaRERA records.
When is possession of NESTOR due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NESTOR in Dronagiri, Raigarh is 29 March 2025 — 27 months later than 30 December 2022, the date given at registration.
Does NESTOR have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of NESTOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KALPANA STRUCT-CON INFRA LLP.
Other projects in pincode 400702
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.