UMA GREENS
by MURUDESHWAR DEVELOPERS · Dronagiri, Raigarh
Possession date of UMA GREENS: 30 September 2026, moved from 30 June 2024 (27 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52000019282. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (September 2026) has passed.
What do you want to know about UMA GREENS?
How the possession date of UMA GREENS has moved
30 June 2024
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT52000019057)
Reason the builder gave MahaRERA: “the construction work was delayed due to unfavorable market conditions & low bookings (Sale of under construction units).”
30 September 2026
Extended at the builder's request (MahaRERA application EA07052620868)
Reason the builder gave MahaRERA: “Delay in Getting Occupancy certificate from Department. Project is completed”
Source: UMA GREENS’s extension records on MahaRERA (P52000019282), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on UMA GREENS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000019282
- Status
- Lapsed (registration period ended)
- Builder
- MURUDESHWAR DEVELOPERS
- Location
- Dronagiri, Raigarh · 400702
- Project type
- Others
- Registered on
- 15 Jan 2019
- Completion date at registration
- June 2024
- Latest completion date
- September 2026
- Delay so far
- 27 months
- Homes
- 46
- Sold or booked
- 59%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of UMA GREENS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| UMA GREENS | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- UMA GREENS: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on UMA GREENS every month.
UMA GREENS: buildings, flats and land, as filed on MahaRERA
- Buildings: UMA GREENS (17 floors, 54 units)
- Car parking: 27 covered
- Land: 1,200 sq m (about 0.3 acres) · sanctioned built-up 1,796 sq m · recreational space 303 sq m
The builder’s record and reviews
Shree RAJ Developers (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 3 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 7 months late); 2 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of UMA GREENS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
UMA GREENS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about UMA GREENS
What is the possession date of UMA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for UMA GREENS in Dronagiri, Raigarh is 30 September 2026 — 27 months later than 30 June 2024, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for UMA GREENS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date UMA GREENS's builder has filed on MahaRERA, the official one, is 30 September 2026, already 27 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of UMA GREENS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), UMA GREENS's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "the construction work was delayed due to unfavorable market conditions & low bookings (Sale of under construction units)."; to 30 September 2026, giving the reason "Delay in Getting Occupancy certificate from Department. Project is completed".
What is the RERA number of UMA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of UMA GREENS in Dronagiri, Raigarh is P52000019282.
Is UMA GREENS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), UMA GREENS is registered as P52000019282 and its status is "Lapsed (registration period ended)".
What is the construction status of UMA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), UMA GREENS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on UMA GREENS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does UMA GREENS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is UMA GREENS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), UMA GREENS is registered on MahaRERA as P52000019282, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if UMA GREENS's possession date changes?
The latest dates are on UMA GREENS's MahaRERA page (P52000019282). GharKundli's Kundli Watch sends a free WhatsApp update on UMA GREENS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does UMA GREENS have?
According to GharKundli's check of MahaRERA records (updated October 2026), UMA GREENS has one building filed: UMA GREENS with 17 floors and 54 units.
How much parking does UMA GREENS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 27 covered car parking spaces for UMA GREENS.
How big is the land of UMA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), UMA GREENS stands on 1,200 sq m of land (about 0.3 acres), with 1,796 sq m of sanctioned built-up area and 303 sq m of recreational open space.
What is the track record of UMA GREENS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree RAJ Developers (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 3 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 7 months late); 2 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of UMA GREENS?
Google Maps has reviews of UMA GREENS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is UMA GREENS?
UMA GREENS by MURUDESHWAR DEVELOPERS is in Dronagiri, Raigarh (pincode 400702), Maharashtra, and is registered on MahaRERA as P52000019282, per GharKundli's check of MahaRERA records.
How many homes are in UMA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), UMA GREENS has 46 homes in 1 tower registered on MahaRERA, and 59% of them are sold or booked.
When was UMA GREENS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), UMA GREENS was registered on MahaRERA on 15 January 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on UMA GREENS?
No court cases are listed for UMA GREENS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of UMA GREENS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MURUDESHWAR DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of UMA GREENS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Raigad →
Other projects in Dronagiri
All 205 projects in Dronagiri (400702) →Other projects by MURUDESHWAR DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.