LAXMI RESIDENCY
by GURUDATTA BUILDERS AND DEVELOPERS LLP · Pushpak (New), Raigarh
Registered on MahaRERA under P52000019760. Status: Completed. Its completion date has moved from June 2021 to December 2022, 18 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
GharKundli’s full report on LAXMI RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000019760
- Status
- Completed
- Builder
- GURUDATTA BUILDERS AND DEVELOPERS LLP
- Location
- Pushpak (New), Raigarh · 410206
- Project type
- Others
- Registered on
- 5 Mar 2019
- Completion date at registration
- June 2021
- Latest completion date
- December 2022
- Delay so far
- 18 months
- Homes
- 16
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
LAXMI RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about LAXMI RESIDENCY
Is LAXMI RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI RESIDENCY is registered as P52000019760 and its status is "Completed".
Where is LAXMI RESIDENCY?
LAXMI RESIDENCY by GURUDATTA BUILDERS AND DEVELOPERS LLP is in Pushpak (New), Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000019760, per GharKundli's check of MahaRERA records.
When is possession of LAXMI RESIDENCY due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for LAXMI RESIDENCY in Pushpak (New), Raigarh is 30 December 2022 — 18 months later than 30 June 2021, the date given at registration.
Does LAXMI RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in LAXMI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI RESIDENCY has 16 homes in 1 tower registered on MahaRERA.
When was LAXMI RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), LAXMI RESIDENCY was registered on MahaRERA on 5 March 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on LAXMI RESIDENCY?
No court cases are listed for LAXMI RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of LAXMI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GURUDATTA BUILDERS AND DEVELOPERS LLP.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.