Sonibai Niwas

by Anant Nathu Gavand · Pushpak New, Raigarh

Registered on MahaRERA under P52000020503. Status: Completed. Its completion date has moved from December 2020 to June 2022, 18 months later.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on Sonibai Niwas

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000020503
Status
Completed
Builder
Anant Nathu Gavand
Location
Pushpak New, Raigarh · 410206
Project type
Others
Registered on
18 Apr 2019
Completion date at registration
December 2020
Latest completion date
June 2022
Delay so far
18 months
Homes
17
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

Sonibai Niwas: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sonibai Niwas

Is Sonibai Niwas registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sonibai Niwas is registered as P52000020503 and its status is "Completed".

Where is Sonibai Niwas?

Sonibai Niwas by Anant Nathu Gavand is in Pushpak New, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000020503, per GharKundli's check of MahaRERA records.

When is possession of Sonibai Niwas due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sonibai Niwas in Pushpak New, Raigarh is 30 June 2022 — 18 months later than 30 December 2020, the date given at registration.

Does Sonibai Niwas have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in Sonibai Niwas?

According to GharKundli's check of MahaRERA records (updated November 2026), Sonibai Niwas has 17 homes in 1 tower registered on MahaRERA.

When was Sonibai Niwas registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sonibai Niwas was registered on MahaRERA on 18 April 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Sonibai Niwas?

No court cases are listed for Sonibai Niwas on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sonibai Niwas?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Anant Nathu Gavand.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.