by ROODRAKSH PROBUILDER AND INFRACON PRIVATE LIMITED · govandi East, Mumbai

Registered on MahaRERA under P51800001113. Status: Completed. Its completion date has moved from December 2019 to March 2022, 27 months later.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on PRATHAM

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800001113
Status
Completed
Builder
ROODRAKSH PROBUILDER AND INFRACON PRIVATE LIMITED
Location
govandi East, Mumbai · 400043
Project type
Residential / Group Housing
Registered on
26 Jul 2017
Completion date at registration
December 2019
Latest completion date
March 2022
Delay so far
27 months
Homes
17
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

PRATHAM: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PRATHAM

Is PRATHAM registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PRATHAM is registered as P51800001113 and its status is "Completed".

Where is PRATHAM?

PRATHAM by ROODRAKSH PROBUILDER AND INFRACON PRIVATE LIMITED is in govandi East, Mumbai (pincode 400043), Maharashtra, and is registered on MahaRERA as P51800001113, per GharKundli's check of MahaRERA records.

When is possession of PRATHAM due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PRATHAM in govandi East, Mumbai is 30 March 2022 — 27 months later than 31 December 2019, the date given at registration.

Does PRATHAM have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in PRATHAM?

According to GharKundli's check of MahaRERA records (updated November 2026), PRATHAM has 17 homes in 1 tower registered on MahaRERA.

When was PRATHAM registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PRATHAM was registered on MahaRERA on 26 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PRATHAM?

No court cases are listed for PRATHAM on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PRATHAM?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ROODRAKSH PROBUILDER AND INFRACON PRIVATE LIMITED.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.