AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD.

by BHOLENATH DEVELOPERS LTD. · Pestom Sagar, MumbaiAlso near Rajawadi, Chembur, Ghatkopar West

Registered on MahaRERA under P51800000759. Status: Completed. Its completion date has moved from June 2018 to December 2020, 30 months later.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD.

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800000759
Status
Completed
Builder
BHOLENATH DEVELOPERS LTD.
Location
Pestom Sagar, Mumbai · 400089
Project type
Residential / Group Housing
Registered on
23 Jul 2017
Completion date at registration
June 2018
Latest completion date
December 2020
Delay so far
30 months
Homes
44
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
3

Kundli Watch

AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD.: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD.

Is AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. is registered as P51800000759 and its status is "Completed".

Where is AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD.?

AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. by BHOLENATH DEVELOPERS LTD. is in Pestom Sagar, Mumbai (pincode 400089), near Rajawadi, Chembur, Ghatkopar West, Maharashtra, and is registered on MahaRERA as P51800000759, per GharKundli's check of MahaRERA records.

When is possession of AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. in Pestom Sagar, Mumbai is 30 December 2020 — 30 months later than 30 June 2018, the date given at registration.

Does AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD.?

According to GharKundli's check of MahaRERA records (updated November 2026), AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. has 44 homes in 1 tower registered on MahaRERA.

When was AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. was registered on MahaRERA on 23 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD.?

1 court case is listed for AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD. on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of AMBAJI NIKETAN CO-OP. HOUSING SOCIETY LTD.?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BHOLENATH DEVELOPERS LTD., which has 3 other projects registered on MahaRERA.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.