by Veer Global Infraconstruction Limited · Umroli East, Palghar

Registered on MahaRERA under P99000034206, and currently active. Its completion date has moved from December 2025 to July 2027, 19 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on VEER 11

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000034206
Status
Registered and active
Builder
Veer Global Infraconstruction Limited
Location
Umroli East, Palghar · 401404
Project type
Residential / Group Housing
Registered on
25 Mar 2022
Completion date at registration
December 2025
Latest completion date
July 2027
Delay so far
19 months
Homes
82
Sold or booked
38%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
8

Kundli Watch

VEER 11: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about VEER 11

Is VEER 11 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VEER 11 is registered as P99000034206 and its status is "Registered and active".

Where is VEER 11?

VEER 11 by Veer Global Infraconstruction Limited is in Umroli East, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000034206, per GharKundli's check of MahaRERA records.

When is possession of VEER 11 due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VEER 11 in Umroli East, Palghar is 31 July 2027 — 19 months later than 31 December 2025, the date given at registration.

Does VEER 11 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of VEER 11?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Veer Global Infraconstruction Limited, which has 8 other projects registered on MahaRERA.

Other projects in pincode 401404

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.