Skip to content
GharKundli

VIVA SWARANGAN

by VIVA HOMES PRIVATE LIMITED · PalgharAlso near navali village

Possession date of VIVA SWARANGAN: 30 April 2027, moved from 30 June 2021 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000008546, and currently active. Its completion date has moved from June 2021 to April 2027: 66 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about VIVA SWARANGAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VIVA SWARANGAN has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT99000010078)

    Reason the builder gave MahaRERA:
    “2. I/ We are highly regretful for the delay in handing over the possession of the above mentioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all t…” Read the full reason“2. I/ We are highly regretful for the delay in handing over the possession of the above mentioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years. In addition, construction activities has severely been affected due to lockdown imposed by concerned authorities, Migration of labor forces and material supply etc. for past 1.5 year.”
  3. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT99000012864)

    Reason the builder gave MahaRERA:
    “The said plot was marked as Garden Reservation under Palghar DP Plan. It was absolute error on the part of the concerning Department, wherein we have made our objection to the said reservation, under our correspondence vide our letters date…” Read the full reason“The said plot was marked as Garden Reservation under Palghar DP Plan. It was absolute error on the part of the concerning Department, wherein we have made our objection to the said reservation, under our correspondence vide our letters dated 26th September 2013, We have submitted our Appeal before the TPA, and its Schedule from Urban Development Department of Proposed Modifications of Substantial Nature of Excluded Part wherein in Schedule Part at serial No. 19 in Modification of Substantial Nature- Modification of Site No. 179 is mention as “Proposed to be deleted and included in Residenti…”
  4. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT99000018109)

    Reason the builder gave MahaRERA:
    “We state and declare that in the on 7th February 2011, we have obtained Commencement certificate for our project, and subsequently on 24th February 2012, we have obtained revised Commencement certificate for the project and have commenced t…” Read the full reason“We state and declare that in the on 7th February 2011, we have obtained Commencement certificate for our project, and subsequently on 24th February 2012, we have obtained revised Commencement certificate for the project and have commenced the constructions work, Subsequent to all the sanctions and permissions by Palghar Nagarparishad, referred hereinabove we have been informed on 7th September 2013, that the said plot on which various sanctions and permissions have been already granted by the sanctioning Authority, the said plot was marked as Garden Reservation under Palghar DP Plan. It was…”
  5. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT99000025641)

    Reason the builder gave MahaRERA:
    “We are highly regretful for the delay in handing over the possession of the above mentioned building due to current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the in…” Read the full reason“We are highly regretful for the delay in handing over the possession of the above mentioned building due to current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years.”
  6. 30 December 2026

    Extended at the builder's request (MahaRERA application EA31122519169)

    Reason the builder gave MahaRERA:
    “We state and declare that in the on 7th February 2011, we have obtained Commencement certificate for our project, and subsequently on 24th February 2012, we have obtained revised Commencement certificate for the project and have commenced t…” Read the full reason“We state and declare that in the on 7th February 2011, we have obtained Commencement certificate for our project, and subsequently on 24th February 2012, we have obtained revised Commencement certificate for the project and have commenced the constructions work, Subsequent to all the sanctions and permissions by Palghar Nagarparishad, referred hereinabove we have been informed on 7th September 2013, that the said plot on which various sanctions and permissions have been already granted by the sanctioning Authority, the said plot was marked as Garden Reservation under Palghar DP Plan. It was…”
  7. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VIVA SWARANGAN’s extension records on MahaRERA (P99000008546), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VIVA SWARANGAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000008546
Status
Registered and active
Builder
VIVA HOMES PRIVATE LIMITED
Location
Palghar · 401404
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
June 2021
Latest completion date
April 2027
Delay so far
66 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
192
Sold or booked
42%
Towers
4
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
11

Construction progress of VIVA SWARANGAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RISHABH100%90%90%34%
SHADAJ100%100%98%70%
GANDHAR100%85%90%34%
MADHYAM100%100%90%34%

Commencement certificate (CC), as filed on MahaRERA

  • RISHABH: covers GR+4th
  • SHADAJ: covers Gr+4th
  • GANDHAR: covers Gr+4th
  • MADHYAM: covers Gr+4th

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VIVA SWARANGAN every month.

VIVA SWARANGAN: buildings, flats and land, as filed on MahaRERA

  • Buildings: RISHABH (5 floors, 58 units) · SHADAJ (5 floors, 58 units) · GANDHAR (5 floors, 38 units) · MADHYAM (5 floors, 38 units)
  • Land: 5,945 sq m (about 1.5 acres) · sanctioned built-up 5,490 sq m · recreational space 331 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Viva Homes (a group of 4 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, 7 past the promised date (typically 36 months late); 10 lapsed. 25 complaints on MahaRERA across 11 projects.

Read Google reviews of VIVA SWARANGAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VIVA SWARANGAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VIVA SWARANGAN

What is the possession date of VIVA SWARANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VIVA SWARANGAN in Palghar is 30 April 2027 — 66 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VIVA SWARANGAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VIVA SWARANGAN's builder has filed on MahaRERA, the official one, is 30 April 2027, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VIVA SWARANGAN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA SWARANGAN's builder applied to MahaRERA to extend the completion date 5 times: to 30 June 2022, giving the reason "2. I/ We are highly regretful for the delay in handing over the possession of the above mentioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years. In addition, construction activities has severely been affected due to lockdown imposed by concerned authorities, Migration of labor forces and material supply etc. for past 1.5 year."; to 30 December 2023, giving the reason "The said plot was marked as Garden Reservation under Palghar DP Plan. It was absolute error on the part of the concerning Department, wherein we have made our objection to the said reservation, under our correspondence vide our letters dated 26th September 2013, We have submitted our Appeal before the TPA, and its Schedule from Urban Development Department of Proposed Modifications of Substantial Nature of Excluded Part wherein in Schedule Part at serial No. 19 in Modification of Substantial Nature- Modification of Site No. 179 is mention as “Proposed to be deleted and included in Residenti…"; to 30 December 2024, giving the reason "We state and declare that in the on 7th February 2011, we have obtained Commencement certificate for our project, and subsequently on 24th February 2012, we have obtained revised Commencement certificate for the project and have commenced the constructions work, Subsequent to all the sanctions and permissions by Palghar Nagarparishad, referred hereinabove we have been informed on 7th September 2013, that the said plot on which various sanctions and permissions have been already granted by the sanctioning Authority, the said plot was marked as Garden Reservation under Palghar DP Plan. It was…"; to 30 December 2025, giving the reason "We are highly regretful for the delay in handing over the possession of the above mentioned building due to current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years."; to 30 December 2026, giving the reason "We state and declare that in the on 7th February 2011, we have obtained Commencement certificate for our project, and subsequently on 24th February 2012, we have obtained revised Commencement certificate for the project and have commenced the constructions work, Subsequent to all the sanctions and permissions by Palghar Nagarparishad, referred hereinabove we have been informed on 7th September 2013, that the said plot on which various sanctions and permissions have been already granted by the sanctioning Authority, the said plot was marked as Garden Reservation under Palghar DP Plan. It was…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of VIVA SWARANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VIVA SWARANGAN in Palghar is P99000008546.

Is VIVA SWARANGAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA SWARANGAN is registered as P99000008546 and its status is "Registered and active".

What is the construction status of VIVA SWARANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA SWARANGAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 85% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does VIVA SWARANGAN have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is VIVA SWARANGAN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA SWARANGAN is registered on MahaRERA as P99000008546, its completion date has moved 66 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VIVA SWARANGAN's possession date changes?

The latest dates are on VIVA SWARANGAN's MahaRERA page (P99000008546). GharKundli's Kundli Watch sends a free WhatsApp update on VIVA SWARANGAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VIVA SWARANGAN have?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA SWARANGAN has 4 buildings filed: RISHABH with 5 floors and 58 units; SHADAJ with 5 floors and 58 units; GANDHAR with 5 floors and 38 units; MADHYAM with 5 floors and 38 units.

How big is the land of VIVA SWARANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA SWARANGAN stands on 5,945 sq m of land (about 1.5 acres), with 5,490 sq m of sanctioned built-up area and 331 sq m of recreational open space.

What is the track record of VIVA SWARANGAN's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Homes (a group of 4 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, 7 past the promised date (typically 36 months late); 10 lapsed. 25 complaints on MahaRERA across 11 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of VIVA SWARANGAN?

Google Maps has reviews of VIVA SWARANGAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VIVA SWARANGAN?

VIVA SWARANGAN by VIVA HOMES PRIVATE LIMITED is in Palghar (pincode 401404), near navali village, Maharashtra, and is registered on MahaRERA as P99000008546, per GharKundli's check of MahaRERA records.

How many homes are in VIVA SWARANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA SWARANGAN has 192 homes in 4 towers registered on MahaRERA, and 42% of them are sold or booked.

When was VIVA SWARANGAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA SWARANGAN was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on VIVA SWARANGAN?

No court cases are listed for VIVA SWARANGAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of VIVA SWARANGAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIVA HOMES PRIVATE LIMITED, which has 11 other projects registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in pincode 401404

All 421 projects in Palghar (401404) →

Other projects by VIVA HOMES PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.