Skip to content
GharKundli

Viva Royal Accord

by Viva Homes Private Limited · Dahisar West, Mumbai 400068Also near Borivali West, Vile Parle East, KandivaliRegistered on MahaRERA as “Royal Accord”

What’s in the report? →

Possession date of Viva Royal Accord (MahaRERA P51800010302): 30 June 2027, moved from 30 December 2021 (66 months later). It has 45 homes (1 BHK and 2 BHK, 451–652 sq ft carpet), 63% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800010302, and currently active.

Source: MahaRERA website — records for P51800010302, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Viva Royal Accord?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Viva Royal Accord has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800011302)

    Reason the builder gave MahaRERA:
    “Due to COVID 19 Pandemic situation, we, the Promoter are facing various difficulties like MCGM new norms & policies like civil aviation etc.,, non-availability of construction material and shortage of labours of etc. and therefore, the Prom…” Read the full reason“Due to COVID 19 Pandemic situation, we, the Promoter are facing various difficulties like MCGM new norms & policies like civil aviation etc.,, non-availability of construction material and shortage of labours of etc. and therefore, the Promoter could not completed the project on time, however, now further plans are approved from MCGM, therefore, we will get further permission at earliest. We have explained this situation to the purchasers and majority has been given their consent for extension of this project and we hereby assure that we will put our best effort to complete the construction…”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800019204)

    Reason the builder gave MahaRERA: “abc”
  4. 30 June 2027

    Extended at the builder's request (MahaRERA application EA19092638943)

    Reason the builder gave MahaRERA:
    “Due to the delay on the part of the Planning Authority in granting the requisite permissions and approvals, coupled with a shortage of funds, there has been a delay in the progress of the Project, however the project shall complete within e…” Read the full reason“Due to the delay on the part of the Planning Authority in granting the requisite permissions and approvals, coupled with a shortage of funds, there has been a delay in the progress of the Project, however the project shall complete within extension time and as per pert chart uploaded herewith”

Source: Viva Royal Accord’s extension records on MahaRERA (P51800010302), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Viva Royal Accord

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800010302
Status
Registered and active
Builder
Viva Homes Private Limited
Location
Dahisar West, Mumbai · 400068
Project type
Others
Registered on
24 Aug 2017
Completion date at registration
December 2021
Latest completion date
June 2027
Delay so far
66 months
Homes
45
Sold or booked
63%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
11

Construction progress of Viva Royal Accord, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Royal Accord100%67%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Royal Accord: covers 12 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Viva Royal Accord every 1–2 months.

Viva Royal Accord: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK45123
2 BHK624 – 65222
Shops130 – 3548

The builder’s record and reviews

Viva Homes (a group of 5 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 17 months); 8 still being built, 7 past the promised date (typically 36 months late); 10 lapsed. 34 complaints on MahaRERA across 13 projects.

Read Google reviews of Viva Royal Accord →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Viva Royal Accord: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Viva Royal Accord

What is the possession date of Viva Royal Accord?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Viva Royal Accord in Dahisar West, Mumbai is 30 June 2027 — 66 months later than 30 December 2021, the date given at registration.

The date has already moved 66 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Viva Royal Accord?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Viva Royal Accord's builder has filed on MahaRERA, the official one, is 30 June 2027, already 66 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Viva Royal Accord extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Royal Accord's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2023, giving the reason "Due to COVID 19 Pandemic situation, we, the Promoter are facing various difficulties like MCGM new norms & policies like civil aviation etc.,, non-availability of construction material and shortage of labours of etc. and therefore, the Promoter could not completed the project on time, however, now further plans are approved from MCGM, therefore, we will get further permission at earliest. We have explained this situation to the purchasers and majority has been given their consent for extension of this project and we hereby assure that we will put our best effort to complete the construction…"; to 31 December 2025, giving the reason "abc"; to 30 June 2027, giving the reason "Due to the delay on the part of the Planning Authority in granting the requisite permissions and approvals, coupled with a shortage of funds, there has been a delay in the progress of the Project, however the project shall complete within extension time and as per pert chart uploaded herewith".

What is the RERA number of Viva Royal Accord?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Viva Royal Accord in Dahisar West, Mumbai is P51800010302.

Is Viva Royal Accord registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Royal Accord is registered as P51800010302 and its status is "Registered and active".

What is the current construction status of Viva Royal Accord? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Royal Accord's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Royal Accord is 67% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Viva Royal Accord have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Viva Royal Accord safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Royal Accord is registered on MahaRERA as P51800010302, its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Viva Royal Accord?

Viva Royal Accord is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Viva Royal Accord are 451 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Viva Royal Accord?

For a flat in Viva Royal Accord (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Viva Royal Accord received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Viva Royal Accord is still under construction, with 30 June 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Viva Royal Accord uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Viva Royal Accord was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Viva Royal Accord's possession date changes?

The latest dates are on Viva Royal Accord's MahaRERA page (P51800010302). GharKundli's Kundli Watch sends a free WhatsApp update on Viva Royal Accord every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Viva Royal Accord have?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Royal Accord has one building filed: Royal Accord with 19 floors and 53 units.

What are the flat sizes (carpet area) in Viva Royal Accord?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Viva Royal Accord: 1 BHK: 451 sq ft carpet (23 homes); 2 BHK: 624 to 652 sq ft carpet (22 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Viva Royal Accord have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 30 covered car parking spaces for Viva Royal Accord.

How big is the land of Viva Royal Accord?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Royal Accord stands on 1,343 sq m of land (about 0.3 acres), with 1,714 sq m of sanctioned built-up area.

What is the track record of Viva Royal Accord's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Homes (a group of 5 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 17 months); 8 still being built, 7 past the promised date (typically 36 months late); 10 lapsed. 34 complaints on MahaRERA across 13 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Viva Royal Accord?

Google Maps has reviews of Viva Royal Accord written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Viva Royal Accord?

Viva Royal Accord by Viva Homes Private Limited is in Dahisar West, Mumbai, pincode 400068 (near Borivali West, Vile Parle East, Kandivali), Maharashtra, and is registered on MahaRERA as P51800010302, per GharKundli's check of MahaRERA records. Its land is filed as CTS no 831 and 846A. GharKundli lists all 180 MahaRERA projects in Dahisar East (400068).

How many flats are in Viva Royal Accord, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Royal Accord has 45 homes in 1 tower registered on MahaRERA, and 63% of them are sold or booked.

When was Viva Royal Accord registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Royal Accord was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Does Viva Royal Accord have any legal issues or court cases?

No court cases are listed for Viva Royal Accord on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Viva Royal Accord?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Viva Homes Private Limited, which has 11 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Dahisar East (400068)

All 180 projects in Dahisar East (400068) →

Other projects by Viva Homes Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.