Skip to content
GharKundli

RAJHANS

by PRATHAM DEVELOPERS · Borivali West, MumbaiAlso near Dahisar East, Dahisar West, Madonna Colony

Possession date of RAJHANS: 30 April 2027, moved from 31 December 2019 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900002771, and currently active. Its completion date has moved from December 2019 to April 2027: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about RAJHANS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of RAJHANS has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51900006040)

    Reason the builder gave MahaRERA: “The reason for delay in completion of project is due to delay caused by supply of materials and services by contractors, market conditions of the Real Estate Sector and prolonged delay in obtaining necessary delay from the Authority.”
  3. 31 January 2024

    Extended at the builder's request (MahaRERA application EXT51900012518)

    Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/01/2024”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA20062621456)

    Reason the builder gave MahaRERA:
    “Due to earlier developers i.e. M/s Prashanti Land Developers inability to complete the project and inability to comply with the requisition of the planning authority the said project got delayed. Now M/s Pratham Developers i.e. We being the…” Read the full reason“Due to earlier developers i.e. M/s Prashanti Land Developers inability to complete the project and inability to comply with the requisition of the planning authority the said project got delayed. Now M/s Pratham Developers i.e. We being the promoter is the duly appointed promoter of the project and have obtained valid Commencement Certificate of the project dated 09/06/2026”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: RAJHANS’s extension records on MahaRERA (P51900002771), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on RAJHANS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900002771
Status
Registered and active
Builder
PRATHAM DEVELOPERS
Location
Borivali West, Mumbai · 400068
Project type
Others
Registered on
4 Aug 2017
Completion date at registration
December 2019
Latest completion date
April 2027
Delay so far
84 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
11
Sold or booked
0%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of RAJHANS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DAHISAR RAJHANS100%45%25%0%

Commencement certificate (CC), as filed on MahaRERA

  • DAHISAR RAJHANS: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAJHANS every month.

RAJHANS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK496 – 5698
2 BHK5573

The builder’s record and reviews

Pratham Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 42 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of RAJHANS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

RAJHANS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about RAJHANS

What is the possession date of RAJHANS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RAJHANS in Borivali West, Mumbai is 30 April 2027 — 84 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for RAJHANS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date RAJHANS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 84 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of RAJHANS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJHANS's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "The reason for delay in completion of project is due to delay caused by supply of materials and services by contractors, market conditions of the Real Estate Sector and prolonged delay in obtaining necessary delay from the Authority."; to 31 January 2024, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/01/2024"; to 31 December 2026, giving the reason "Due to earlier developers i.e. M/s Prashanti Land Developers inability to complete the project and inability to comply with the requisition of the planning authority the said project got delayed. Now M/s Pratham Developers i.e. We being the promoter is the duly appointed promoter of the project and have obtained valid Commencement Certificate of the project dated 09/06/2026". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of RAJHANS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RAJHANS in Borivali West, Mumbai is P51900002771.

Is RAJHANS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJHANS is registered as P51900002771 and its status is "Registered and active".

What is the construction status of RAJHANS?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJHANS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DAHISAR RAJHANS is 45% done and internal work 25%. GharKundli's full report compares construction progress with the deadline.

Does RAJHANS have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is RAJHANS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJHANS is registered on MahaRERA as P51900002771, its completion date has moved 84 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if RAJHANS's possession date changes?

The latest dates are on RAJHANS's MahaRERA page (P51900002771). GharKundli's Kundli Watch sends a free WhatsApp update on RAJHANS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does RAJHANS have?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJHANS has one building filed: DAHISAR RAJHANS with 11 floors and 11 units.

What are the flat sizes (carpet area) in RAJHANS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for RAJHANS: 1 BHK: 496 to 569 sq ft carpet (8 homes); 2 BHK: 557 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of RAJHANS?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJHANS stands on 757 sq m of land (about 0.2 acres), with 1,998 sq m of sanctioned built-up area.

What is the track record of RAJHANS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Pratham Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 42 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of RAJHANS?

Google Maps has reviews of RAJHANS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is RAJHANS?

RAJHANS by PRATHAM DEVELOPERS is in Borivali West, Mumbai (pincode 400068), near Dahisar East, Dahisar West, Madonna Colony, Maharashtra, and is registered on MahaRERA as P51900002771, per GharKundli's check of MahaRERA records.

How many homes are in RAJHANS?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJHANS has 11 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was RAJHANS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJHANS was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on RAJHANS?

No court cases are listed for RAJHANS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of RAJHANS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRATHAM DEVELOPERS, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Borivali West

All 180 projects in Dahisar East (400068) →

Other projects by PRATHAM DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.