RITE DEVANGI

by YASHODANAND INFRA (AND) · Borivali West, MumbaiAlso near Borivali East, Mandapeshwar

Possession date of RITE DEVANGI: 25 March 2027, moved from 30 October 2024 (25 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800051848, and currently active. Its completion date has moved from October 2024 to March 2027: 25 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about RITE DEVANGI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of RITE DEVANGI has moved

  1. 30 October 2024

    Completion date given when the project was registered

  2. 30 October 2025

    Extended at the builder's request (MahaRERA application EXT51800025042)

    Reason the builder gave MahaRERA: “Due to shortage of material and labor not able to complete project please grant us extension till 30/10/2025”
  3. 25 November 2026

    Extended at the builder's request (MahaRERA application EA11082622095)

    Reason the builder gave MahaRERA: “OC Recived”
  4. 25 March 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: RITE DEVANGI’s extension records on MahaRERA (P51800051848), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on RITE DEVANGI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800051848
Status
Registered and active
Builder
YASHODANAND INFRA
Location
Borivali West, Mumbai · 400092
Project type
Residential / Group Housing
Registered on
7 Jul 2023
Completion date at registration
October 2024
Latest completion date
March 2027
Delay so far
25 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
40
Sold or booked
71%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of RITE DEVANGI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RITE DEVANGI100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • RITE DEVANGI: covers Stilt + 1st to 10th upper floors + LMR/OHT

Latest CC order on MahaRERA: dated 30/04/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on RITE DEVANGI every month.

RITE DEVANGI: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK392 – 53722
2 BHK537 – 79718
  • Buildings: RITE DEVANGI (11 floors, 40 units)
  • Car parking: 22 covered
  • Land: 701 sq m (about 0.2 acres) · sanctioned built-up 2,017 sq m

The builder’s record and reviews

Yashodanand Infra (a group of 5 linked companies) has 7 projects on MahaRERA since 2022, this one included. Of the 7 GharKundli has checked: 7 still being built, 3 past the promised date (typically 20 months late). No complaints on MahaRERA.

Read Google reviews of RITE DEVANGI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

RITE DEVANGI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about RITE DEVANGI

What is the possession date of RITE DEVANGI?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RITE DEVANGI in Borivali West, Mumbai is 25 March 2027 — 25 months later than 30 October 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for RITE DEVANGI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date RITE DEVANGI's builder has filed on MahaRERA, the official one, is 25 March 2027, already 25 months later than the 30 October 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of RITE DEVANGI extended?

According to GharKundli's check of MahaRERA records (updated October 2026), RITE DEVANGI's builder applied to MahaRERA to extend the completion date 2 times: to 30 October 2025, giving the reason "Due to shortage of material and labor not able to complete project please grant us extension till 30/10/2025"; to 25 November 2026, giving the reason "OC Recived". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of RITE DEVANGI?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RITE DEVANGI in Borivali West, Mumbai is P51800051848.

Is RITE DEVANGI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RITE DEVANGI is registered as P51800051848 and its status is "Registered and active".

What is the construction status of RITE DEVANGI?

According to GharKundli's check of MahaRERA records (updated October 2026), RITE DEVANGI's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RITE DEVANGI is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does RITE DEVANGI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is RITE DEVANGI safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), RITE DEVANGI is registered on MahaRERA as P51800051848, its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if RITE DEVANGI's possession date changes?

The latest dates are on RITE DEVANGI's MahaRERA page (P51800051848). GharKundli's Kundli Watch sends a free WhatsApp update on RITE DEVANGI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does RITE DEVANGI have?

According to GharKundli's check of MahaRERA records (updated October 2026), RITE DEVANGI has one building filed: RITE DEVANGI with 11 floors and 40 units.

What are the flat sizes (carpet area) in RITE DEVANGI?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for RITE DEVANGI: 1 BHK: 392 to 537 sq ft carpet (22 homes); 2 BHK: 537 to 797 sq ft carpet (18 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does RITE DEVANGI have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 22 covered car parking spaces for RITE DEVANGI.

How big is the land of RITE DEVANGI?

According to GharKundli's check of MahaRERA records (updated October 2026), RITE DEVANGI stands on 701 sq m of land (about 0.2 acres), with 2,017 sq m of sanctioned built-up area.

What is the track record of RITE DEVANGI's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashodanand Infra (a group of 5 linked companies) has 7 projects on MahaRERA since 2022, this one included. Of the 7 GharKundli has checked: 7 still being built, 3 past the promised date (typically 20 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of RITE DEVANGI?

Google Maps has reviews of RITE DEVANGI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is RITE DEVANGI?

RITE DEVANGI by YASHODANAND INFRA (AND) is in Borivali West, Mumbai (pincode 400092), near Borivali East, Mandapeshwar, Maharashtra, and is registered on MahaRERA as P51800051848, per GharKundli's check of MahaRERA records.

How many homes are in RITE DEVANGI?

According to GharKundli's check of MahaRERA records (updated October 2026), RITE DEVANGI has 40 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.

When was RITE DEVANGI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RITE DEVANGI was registered on MahaRERA on 7 July 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on RITE DEVANGI?

No court cases are listed for RITE DEVANGI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of RITE DEVANGI?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is YASHODANAND INFRA, the company AND files this project under, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400092

All 362 projects in Borivali West (400092) →

Other projects by YASHODANAND INFRA

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.