SONI ARCADE, BUILDING NO 2
by SONI & ASSOCIATES · Borivali West, MumbaiAlso near Babhai Naka
Possession date of SONI ARCADE, BUILDING NO 2: 31 December 2026, moved from 31 December 2018 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800013002, and currently active. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SONI ARCADE, BUILDING NO 2?
How the possession date of SONI ARCADE, BUILDING NO 2 has moved
31 December 2018
Completion date given when the project was registered
31 December 2021
Extended at the builder's request (MahaRERA application EXT51800000762)
Reason the builder gave MahaRERA: “Pending of some approvals”
31 December 2021
Extended at the builder's request (MahaRERA application EXT51800005304)
Reason the builder gave MahaRERA: “Due to lack of fund and permission issues project is been delayed”
30 June 2025
Extended at the builder's request (MahaRERA application EXT51800012783)
Reason the builder gave MahaRERA: “Due to Covid and changes in the Plan we where not able to complete the Project in time.”
31 March 2026
Extended at the builder's request (MahaRERA application EA22082502413)
Reason the builder gave MahaRERA: “Death of Partner and changes in promoter from partnership firm to Proprietor.”
30 June 2026
Extended at the builder's request (MahaRERA application EA14042620631)
Reason the builder gave MahaRERA: “waiting of receipt of Full OC”
31 December 2026
Extended at the builder's request (MahaRERA application EA31072621951)
Reason the builder gave MahaRERA:
“At the outset, we submit that the construction and development work of the project has been substantially completed. Further, an application for issuance of Occupancy Certificate (OC) has already been submitted to the Competent Authority on…” Read the full reason
“At the outset, we submit that the construction and development work of the project has been substantially completed. Further, an application for issuance of Occupancy Certificate (OC) has already been submitted to the Competent Authority on 30.06.2026. We further submit that the Competent Authority is presently processing the said application and we have been informed that the Completion Certificate / Occupancy Certificate is expected to be issued shortly. We anticipate receiving the requisite certificate within a period of approximately four weeks. Immediately upon receipt of the same, a c…”
Source: SONI ARCADE, BUILDING NO 2’s extension records on MahaRERA (P51800013002), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SONI ARCADE, BUILDING NO 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 1 court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800013002
- Status
- Registered and active
- Builder
- SONI & ASSOCIATES
- Location
- Borivali West, Mumbai · 400092
- Project type
- Others
- Registered on
- 11 Sep 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2026
- Delay so far
- 96 months
- Homes
- 55
- Sold or booked
- 83%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 1
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of SONI ARCADE, BUILDING NO 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SONI ARCADE II | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- SONI ARCADE II: covers 23 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SONI ARCADE, BUILDING NO 2 every month.
SONI ARCADE, BUILDING NO 2: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 636 – 778 | 35 |
| 1 BHK | 458 – 636 | 20 |
| Office Space | 501 – 770 | 9 |
| Shops | 256 – 453 | 5 |
- Buildings: SONI ARCADE II (23 floors, 69 units)
- Car parking: 62 covered
- Land: 3,544 sq m (about 0.9 acres) · sanctioned built-up 3,606 sq m
- Boundaries filed include: PRIMARY SCHOOL
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SONI ARCADE, BUILDING NO 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SONI ARCADE, BUILDING NO 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SONI ARCADE, BUILDING NO 2
What is the possession date of SONI ARCADE, BUILDING NO 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SONI ARCADE, BUILDING NO 2 in Borivali West, Mumbai is 31 December 2026 — 96 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SONI ARCADE, BUILDING NO 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SONI ARCADE, BUILDING NO 2's builder has filed on MahaRERA, the official one, is 31 December 2026, already 96 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SONI ARCADE, BUILDING NO 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SONI ARCADE, BUILDING NO 2's builder applied to MahaRERA to extend the completion date 6 times: to 31 December 2021, giving the reason "Pending of some approvals"; to 31 December 2021, giving the reason "Due to lack of fund and permission issues project is been delayed"; to 30 June 2025, giving the reason "Due to Covid and changes in the Plan we where not able to complete the Project in time."; to 31 March 2026, giving the reason "Death of Partner and changes in promoter from partnership firm to Proprietor."; to 30 June 2026, giving the reason "waiting of receipt of Full OC"; to 31 December 2026, giving the reason "At the outset, we submit that the construction and development work of the project has been substantially completed. Further, an application for issuance of Occupancy Certificate (OC) has already been submitted to the Competent Authority on 30.06.2026. We further submit that the Competent Authority is presently processing the said application and we have been informed that the Completion Certificate / Occupancy Certificate is expected to be issued shortly. We anticipate receiving the requisite certificate within a period of approximately four weeks. Immediately upon receipt of the same, a c…".
What is the RERA number of SONI ARCADE, BUILDING NO 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SONI ARCADE, BUILDING NO 2 in Borivali West, Mumbai is P51800013002.
Is SONI ARCADE, BUILDING NO 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SONI ARCADE, BUILDING NO 2 is registered as P51800013002 and its status is "Registered and active".
What is the construction status of SONI ARCADE, BUILDING NO 2?
According to GharKundli's check of MahaRERA records (updated October 2026), SONI ARCADE, BUILDING NO 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SONI ARCADE II is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SONI ARCADE, BUILDING NO 2 have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SONI ARCADE, BUILDING NO 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SONI ARCADE, BUILDING NO 2 is registered on MahaRERA as P51800013002, its completion date has moved 96 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SONI ARCADE, BUILDING NO 2's possession date changes?
The latest dates are on SONI ARCADE, BUILDING NO 2's MahaRERA page (P51800013002). GharKundli's Kundli Watch sends a free WhatsApp update on SONI ARCADE, BUILDING NO 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SONI ARCADE, BUILDING NO 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), SONI ARCADE, BUILDING NO 2 has one building filed: SONI ARCADE II with 23 floors and 69 units.
What are the flat sizes (carpet area) in SONI ARCADE, BUILDING NO 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SONI ARCADE, BUILDING NO 2: 2 BHK: 636 to 778 sq ft carpet (35 homes); 1 BHK: 458 to 636 sq ft carpet (20 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SONI ARCADE, BUILDING NO 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 62 covered car parking spaces for SONI ARCADE, BUILDING NO 2.
How big is the land of SONI ARCADE, BUILDING NO 2?
According to GharKundli's check of MahaRERA records (updated October 2026), SONI ARCADE, BUILDING NO 2 stands on 3,544 sq m of land (about 0.9 acres), with 3,606 sq m of sanctioned built-up area.
Where can I read reviews of SONI ARCADE, BUILDING NO 2?
Google Maps has reviews of SONI ARCADE, BUILDING NO 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SONI ARCADE, BUILDING NO 2?
SONI ARCADE, BUILDING NO 2 by SONI & ASSOCIATES is in Borivali West, Mumbai (pincode 400092), near Babhai Naka, Maharashtra, and is registered on MahaRERA as P51800013002, per GharKundli's check of MahaRERA records. Its boundaries filed there include PRIMARY SCHOOL.
How many homes are in SONI ARCADE, BUILDING NO 2?
According to GharKundli's check of MahaRERA records (updated October 2026), SONI ARCADE, BUILDING NO 2 has 55 homes in 1 tower registered on MahaRERA, and 83% of them are sold or booked.
When was SONI ARCADE, BUILDING NO 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SONI ARCADE, BUILDING NO 2 was registered on MahaRERA on 11 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SONI ARCADE, BUILDING NO 2?
1 court case is listed for SONI ARCADE, BUILDING NO 2 on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SONI ARCADE, BUILDING NO 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SONI & ASSOCIATES.
Check it yourself on MahaRERA
- How to check the possession date of SONI ARCADE, BUILDING NO 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400092
- FORTUNE AVIRAHI WING A
- Sparkle Umadarshan
- RITE DEVANGI
- SHRADDHA SKYLINE
- I SPACE URBAN VISTA
- GAURAV GALAXY
- SKYLARK HEIGHTS
- Hiranandani Bluecrest
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.