by SPARKLE EARTH DEVELOPER · Borivali West, Mumbai 400092Also near Borivali East, Mandapeshwar

What’s in the report? →

Possession date of Sparkle Umadarshan (MahaRERA P51800051376): 31 December 2026, moved from 31 December 2025 (12 months later). It has 28 homes (1 BHK, 2 BHK and 3 BHK, 228–718 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800051376, and currently active.

Source: MahaRERA website — records for P51800051376, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Sparkle Umadarshan?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Sparkle Umadarshan has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA20122518859)

    Reason the builder gave MahaRERA:
    “We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the fol…” Read the full reason“We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: 1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and quality. 2. Delay in Statutory Clearances/Utility Approvals Excel W 19 KB We woul…”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA11092622526)

    Reason the builder gave MahaRERA:
    “1. Structural Redesign or Change in Planning I Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term saf…” Read the full reason“1. Structural Redesign or Change in Planning I Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and quality. 2. Delay in Statutory Clearances/Utility Approvals The redesigning and revised approvals of the plans had to be procured from BMC, and other government authorities which led to a delay in the commencement of construction, which impacted construction timelines despite our continuous follow-up. 3. Unforeseen Soil Conditions During the excav…”

Source: Sparkle Umadarshan’s extension records on MahaRERA (P51800051376), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sparkle Umadarshan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800051376
Status
Registered and active
Builder
SPARKLE EARTH DEVELOPER
Location
Borivali West, Mumbai · 400092
Project type
Others
Registered on
8 Jun 2023
Completion date at registration
December 2025
Latest completion date
December 2026
Delay so far
12 months
Homes
28
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Sparkle Umadarshan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sparkle Umadarshan100%100%85%0%

Commencement certificate (CC), as filed on MahaRERA

  • Sparkle Umadarshan: covers Ground (part) + Stilt (part) + 1st floor + 2nd for service floor + 3rd to 8th + 9th Part upper floors

Latest CC order on MahaRERA: dated 20/01/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sparkle Umadarshan every 1–2 months.

Sparkle Umadarshan: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK485 – 64625
Shops136 – 3155
Office Space1,235 – 1,3262
Other2281
1 BHK2981
3 BHK7181
  • Buildings: Sparkle Umadarshan (10 floors, 35 units)
  • Car parking: 26 covered
  • Land: 687 sq m (about 0.2 acres) · sanctioned built-up 2,032 sq m
  • Boundaries filed include: Shimpoli Road
  • Land, as filed: 719D
  • Map: Get directions

The builder’s record and reviews

Sparkle Earth Developer has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 3 months); 2 still being built, 1 past the promised date (typically 10 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Sparkle Umadarshan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sparkle Umadarshan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sparkle Umadarshan

What is the possession date of Sparkle Umadarshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sparkle Umadarshan in Borivali West, Mumbai is 31 December 2026 — 12 months later than 31 December 2025, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Sparkle Umadarshan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sparkle Umadarshan's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sparkle Umadarshan extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Umadarshan's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: 1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and quality. 2. Delay in Statutory Clearances/Utility Approvals Excel W 19 KB We woul…"; to 31 December 2026, giving the reason "1. Structural Redesign or Change in Planning I Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and quality. 2. Delay in Statutory Clearances/Utility Approvals The redesigning and revised approvals of the plans had to be procured from BMC, and other government authorities which led to a delay in the commencement of construction, which impacted construction timelines despite our continuous follow-up. 3. Unforeseen Soil Conditions During the excav…".

What is the RERA number of Sparkle Umadarshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sparkle Umadarshan in Borivali West, Mumbai is P51800051376.

Is Sparkle Umadarshan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Umadarshan is registered as P51800051376 and its status is "Registered and active".

What is the current construction status of Sparkle Umadarshan? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Umadarshan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sparkle Umadarshan is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does Sparkle Umadarshan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sparkle Umadarshan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Umadarshan is registered on MahaRERA as P51800051376, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sparkle Umadarshan?

Sparkle Umadarshan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Sparkle Umadarshan are 228 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sparkle Umadarshan?

For a flat in Sparkle Umadarshan (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Sparkle Umadarshan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Umadarshan is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Sparkle Umadarshan a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Umadarshan is a redevelopment: 22 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Sparkle Umadarshan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sparkle Umadarshan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sparkle Umadarshan's possession date changes?

The latest dates are on Sparkle Umadarshan's MahaRERA page (P51800051376). GharKundli's Kundli Watch sends a free WhatsApp update on Sparkle Umadarshan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sparkle Umadarshan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Umadarshan has one building filed: Sparkle Umadarshan with 10 floors and 35 units.

What are the flat sizes (carpet area) in Sparkle Umadarshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sparkle Umadarshan: 2 BHK: 485 to 646 sq ft carpet (25 homes); Other: 228 sq ft carpet (1 homes); 1 BHK: 298 sq ft carpet (1 homes); 3 BHK: 718 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Sparkle Umadarshan have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 26 covered car parking spaces for Sparkle Umadarshan.

How big is the land of Sparkle Umadarshan?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Umadarshan stands on 687 sq m of land (about 0.2 acres), with 2,032 sq m of sanctioned built-up area.

What is the track record of Sparkle Umadarshan's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Earth Developer has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 3 months); 2 still being built, 1 past the promised date (typically 10 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Sparkle Umadarshan?

Google Maps has reviews of Sparkle Umadarshan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sparkle Umadarshan?

Sparkle Umadarshan by SPARKLE EARTH DEVELOPER is in Borivali West, Mumbai, pincode 400092 (near Borivali East, Mandapeshwar), Maharashtra, and is registered on MahaRERA as P51800051376, per GharKundli's check of MahaRERA records. Its boundaries filed there include Shimpoli Road. Its land is filed as 719D. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).

How many flats are in Sparkle Umadarshan, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Umadarshan has 28 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Sparkle Umadarshan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sparkle Umadarshan was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.

Does Sparkle Umadarshan have any legal issues or court cases?

No court cases are listed for Sparkle Umadarshan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Sparkle Umadarshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SPARKLE EARTH DEVELOPER, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Borivali West (400092)

All 362 projects in Borivali West (400092) →

Other projects by SPARKLE EARTH DEVELOPER

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.