AVYUKTA PARIJAT
by SHIVOHAM INFRAHOMES LLP · Borivali West, MumbaiAlso near Eksar, Kandivali, Vile Parle East
Possession date of AVYUKTA PARIJAT: 31 July 2030, moved from 30 April 2027 (35 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800081115, and currently active. Its completion date has moved from April 2027 to July 2030: 35 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about AVYUKTA PARIJAT?
How the possession date of AVYUKTA PARIJAT has moved
30 April 2027
Completion date given when the project was registered
31 March 2030
Extended at the builder's request (MahaRERA application EA08092622480)
Reason the builder gave MahaRERA:
“The delay in the implementation of Avyukta Parijat Redevelopment project is attributable to the subsequent inclusion and consolidation of the adjoining Akshar CHSL & Ateka CHSL societies dated 29th November and 30th December 2024 respective…” Read the full reason
“The delay in the implementation of Avyukta Parijat Redevelopment project is attributable to the subsequent inclusion and consolidation of the adjoining Akshar CHSL & Ateka CHSL societies dated 29th November and 30th December 2024 respectively, undertaken to achieve greater project scale, planning efficiency, development potential and enhanced benefits for all the stakeholders. The extended timeline was necessitated by the additional society- level approvals, documentation, due — diligence, integration of redevelopment terms and regulatory compliance arising from their late-stage inclusion”31 July 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: AVYUKTA PARIJAT’s extension records on MahaRERA (P51800081115), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AVYUKTA PARIJAT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800081115
- Status
- Registered and active
- Builder
- SHIVOHAM INFRAHOMES LLP
- Location
- Borivali West, Mumbai · 400091
- Project type
- Others
- Registered on
- 30 Mar 2026
- Completion date at registration
- April 2027
- Latest completion date
- July 2030
- Delay so far
- 35 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 34
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of AVYUKTA PARIJAT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AVYUKTA PARIJAT | 100% | 30% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- AVYUKTA PARIJAT: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AVYUKTA PARIJAT every month.
AVYUKTA PARIJAT: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 793 – 847 | 20 |
| 2 BHK | 522 – 638 | 13 |
| 4 BHK | 1,068 | 1 |
- Buildings: AVYUKTA PARIJAT (8 floors, 34 units)
- Car parking: 35 covered
- Land: 1,776 sq m (about 0.4 acres) · sanctioned built-up 2,085 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shivoham Infrahomes (a group of 4 linked companies) has 12 projects on MahaRERA since 2021, this one included. Of the 12 GharKundli has checked: 4 finished, all within the promised date; 8 still being built, none past the promised date yet. 3 complaints on MahaRERA across 2 projects.
Read Google reviews of AVYUKTA PARIJAT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AVYUKTA PARIJAT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AVYUKTA PARIJAT
What is the possession date of AVYUKTA PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AVYUKTA PARIJAT in Borivali West, Mumbai is 31 July 2030 — 35 months later than 30 April 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for AVYUKTA PARIJAT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AVYUKTA PARIJAT's builder has filed on MahaRERA, the official one, is 31 July 2030, already 35 months later than the 30 April 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AVYUKTA PARIJAT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AVYUKTA PARIJAT's builder applied to MahaRERA to extend the completion date once: to 31 March 2030, giving the reason "The delay in the implementation of Avyukta Parijat Redevelopment project is attributable to the subsequent inclusion and consolidation of the adjoining Akshar CHSL & Ateka CHSL societies dated 29th November and 30th December 2024 respectively, undertaken to achieve greater project scale, planning efficiency, development potential and enhanced benefits for all the stakeholders. The extended timeline was necessitated by the additional society- level approvals, documentation, due — diligence, integration of redevelopment terms and regulatory compliance arising from their late-stage inclusion". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of AVYUKTA PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AVYUKTA PARIJAT in Borivali West, Mumbai is P51800081115.
Is AVYUKTA PARIJAT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AVYUKTA PARIJAT is registered as P51800081115 and its status is "Registered and active".
What is the construction status of AVYUKTA PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), AVYUKTA PARIJAT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AVYUKTA PARIJAT is 30% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does AVYUKTA PARIJAT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is AVYUKTA PARIJAT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AVYUKTA PARIJAT is registered on MahaRERA as P51800081115, its completion date has moved 35 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AVYUKTA PARIJAT's possession date changes?
The latest dates are on AVYUKTA PARIJAT's MahaRERA page (P51800081115). GharKundli's Kundli Watch sends a free WhatsApp update on AVYUKTA PARIJAT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AVYUKTA PARIJAT have?
According to GharKundli's check of MahaRERA records (updated October 2026), AVYUKTA PARIJAT has one building filed: AVYUKTA PARIJAT with 8 floors and 34 units.
What are the flat sizes (carpet area) in AVYUKTA PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for AVYUKTA PARIJAT: 3 BHK: 793 to 847 sq ft carpet (20 homes); 2 BHK: 522 to 638 sq ft carpet (13 homes); 4 BHK: 1068 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does AVYUKTA PARIJAT have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 35 covered car parking spaces for AVYUKTA PARIJAT.
How big is the land of AVYUKTA PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), AVYUKTA PARIJAT stands on 1,776 sq m of land (about 0.4 acres), with 2,085 sq m of sanctioned built-up area.
What is the track record of AVYUKTA PARIJAT's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Infrahomes (a group of 4 linked companies) has 12 projects on MahaRERA since 2021, this one included. Of the 12 GharKundli has checked: 4 finished, all within the promised date; 8 still being built, none past the promised date yet. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of AVYUKTA PARIJAT?
Google Maps has reviews of AVYUKTA PARIJAT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AVYUKTA PARIJAT?
AVYUKTA PARIJAT by SHIVOHAM INFRAHOMES LLP is in Borivali West, Mumbai (pincode 400091), near Eksar, Kandivali, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800081115, per GharKundli's check of MahaRERA records.
How many homes are in AVYUKTA PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), AVYUKTA PARIJAT has 34 homes in 1 tower registered on MahaRERA.
When was AVYUKTA PARIJAT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AVYUKTA PARIJAT was registered on MahaRERA on 30 March 2026. GharKundli did not find a title report on the land on file there.
Are there court cases on AVYUKTA PARIJAT?
No court cases are listed for AVYUKTA PARIJAT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AVYUKTA PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIVOHAM INFRAHOMES LLP, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of AVYUKTA PARIJAT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai Suburban →
Other projects in pincode 400091
- SAI KRUPA CHSL REDEVELOPED
- BORIVALI VEER DHAVAL
- BHOOMI PRATISHTHA
- BANK OF INDIA EMPLOYEES SUKHADA CHSL
- RASHMI SQUARE
- LEGACY
- Kaustubh Capital
- DTG AZURE
Other projects by SHIVOHAM INFRAHOMES LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.