RASHMI SQUARE
by Modi's Navnirman Limited · Borivali West, MumbaiAlso near Eksar Village, Kandivali, Vile Parle East
Possession date of RASHMI SQUARE: 28 September 2027, moved from 28 May 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800054722, and currently active. Its completion date has moved from May 2026 to September 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about RASHMI SQUARE?
How the possession date of RASHMI SQUARE has moved
28 May 2026
Completion date given when the project was registered
28 May 2027
Extended at the builder's request (MahaRERA application EA28052621136)
Reason the builder gave MahaRERA:
“We, MODIS NAVNIRMAN LTD, are the promoters of the real estate project known as "RASHMI SQUARE" bearing Maha RERA Registration No. P51800054722. The delay in the completion of the aforesaid project has primarily arisen on account of discrepa…” Read the full reason
“We, MODIS NAVNIRMAN LTD, are the promoters of the real estate project known as "RASHMI SQUARE" bearing Maha RERA Registration No. P51800054722. The delay in the completion of the aforesaid project has primarily arisen on account of discrepancies observed in the land area as reflected in the official records vis-à-vis the actual land particulars required for the project. The resolution of these discrepancies necessitated detailed verification, reconciliation of records, and procedural compliance with the concerned authorities before further progress on the project could be undertaken. The pr…”28 September 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: RASHMI SQUARE’s extension records on MahaRERA (P51800054722), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RASHMI SQUARE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800054722
- Status
- Registered and active
- Builder
- Modi's Navnirman Limited
- Location
- Borivali West, Mumbai · 400091
- Project type
- Others
- Registered on
- 6 Feb 2024
- Completion date at registration
- May 2026
- Latest completion date
- September 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 130
- Sold or booked
- 53%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of RASHMI SQUARE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A WING | 100% | 90% | 75% | 75% |
| B WING | 100% | 90% | 75% | 75% |
Commencement certificate (CC), as filed on MahaRERA
- A WING: covers Wing ‘A’ & ‘B’ comprising of Wing-A (Part) Ground Floor + (Part) Stilt + 1st Floor + 2nd & 3rd Podium floor + Amenity floor + 1st to 17th upper floors + LMR + O
- B WING: covers Wing ‘A’ & ‘B’ comprising of Wing-A (Part) Ground Floor + (Part) Stilt + 1st Floor + 2nd & 3rd Podium floor + Amenity floor + 1st to 17th upper floors + LMR + O
Latest CC order on MahaRERA: dated 03/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RASHMI SQUARE every month.
RASHMI SQUARE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 442 – 774 | 80 |
| 1 BHK | 333 – 442 | 33 |
| 3 BHK | 749 – 774 | 15 |
| Shops | 206 – 576 | 9 |
| 4 BHK | 1,310 – 1,430 | 2 |
| Office Space | 854 – 1,119 | 2 |
| Other | 884 | 1 |
- Buildings: A WING (21 floors, 77 units) · B WING (21 floors, 65 units)
- Car parking: 143 covered
- Land: 2,478 sq m (about 0.6 acres) · sanctioned built-up 8,358 sq m
- Boundaries filed include: Jay Kamakshi Society, Yoganand Society
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Modi's Navnirman (a group of 2 linked companies) has 12 projects on MahaRERA since 2021, this one included. Of the 11 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 3 months); 7 still being built, 2 past the promised date (typically 8 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of RASHMI SQUARE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RASHMI SQUARE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RASHMI SQUARE
What is the possession date of RASHMI SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RASHMI SQUARE in Borivali West, Mumbai is 28 September 2027 — 12 months later than 28 May 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for RASHMI SQUARE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RASHMI SQUARE's builder has filed on MahaRERA, the official one, is 28 September 2027, already 12 months later than the 28 May 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RASHMI SQUARE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), RASHMI SQUARE's builder applied to MahaRERA to extend the completion date once: to 28 May 2027, giving the reason "We, MODIS NAVNIRMAN LTD, are the promoters of the real estate project known as "RASHMI SQUARE" bearing Maha RERA Registration No. P51800054722. The delay in the completion of the aforesaid project has primarily arisen on account of discrepancies observed in the land area as reflected in the official records vis-à-vis the actual land particulars required for the project. The resolution of these discrepancies necessitated detailed verification, reconciliation of records, and procedural compliance with the concerned authorities before further progress on the project could be undertaken. The pr…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of RASHMI SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RASHMI SQUARE in Borivali West, Mumbai is P51800054722.
Is RASHMI SQUARE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RASHMI SQUARE is registered as P51800054722 and its status is "Registered and active".
What is the construction status of RASHMI SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), RASHMI SQUARE's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 90% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does RASHMI SQUARE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is RASHMI SQUARE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), RASHMI SQUARE is registered on MahaRERA as P51800054722, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RASHMI SQUARE's possession date changes?
The latest dates are on RASHMI SQUARE's MahaRERA page (P51800054722). GharKundli's Kundli Watch sends a free WhatsApp update on RASHMI SQUARE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RASHMI SQUARE have?
According to GharKundli's check of MahaRERA records (updated October 2026), RASHMI SQUARE has 2 buildings filed: A WING with 21 floors and 77 units; B WING with 21 floors and 65 units.
What are the flat sizes (carpet area) in RASHMI SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for RASHMI SQUARE: 2 BHK: 442 to 774 sq ft carpet (80 homes); 1 BHK: 333 to 442 sq ft carpet (33 homes); 3 BHK: 749 to 774 sq ft carpet (15 homes); 4 BHK: 1310 to 1430 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does RASHMI SQUARE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 143 covered car parking spaces for RASHMI SQUARE.
How big is the land of RASHMI SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), RASHMI SQUARE stands on 2,478 sq m of land (about 0.6 acres), with 8,358 sq m of sanctioned built-up area.
What is the track record of RASHMI SQUARE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi's Navnirman (a group of 2 linked companies) has 12 projects on MahaRERA since 2021, this one included. Of the 11 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 3 months); 7 still being built, 2 past the promised date (typically 8 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of RASHMI SQUARE?
Google Maps has reviews of RASHMI SQUARE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RASHMI SQUARE?
RASHMI SQUARE by Modi's Navnirman Limited is in Borivali West, Mumbai (pincode 400091), near Eksar Village, Kandivali, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800054722, per GharKundli's check of MahaRERA records. Its boundaries filed there include Jay Kamakshi Society, Yoganand Society.
How many homes are in RASHMI SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), RASHMI SQUARE has 130 homes in 2 towers registered on MahaRERA, and 53% of them are sold or booked.
When was RASHMI SQUARE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RASHMI SQUARE was registered on MahaRERA on 6 February 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on RASHMI SQUARE?
No court cases are listed for RASHMI SQUARE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of RASHMI SQUARE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Modi's Navnirman Limited, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of RASHMI SQUARE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400091
- SAI KRUPA CHSL REDEVELOPED
- BORIVALI VEER DHAVAL
- BHOOMI PRATISHTHA
- BANK OF INDIA EMPLOYEES SUKHADA CHSL
- LEGACY
- Kaustubh Capital
- AVYUKTA PARIJAT
- DTG AZURE
Other projects by Modi's Navnirman Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.