Modi Rashmi Celestia
by Modi's Navnirman Limited · Borivali West, Mumbai 400092Also near Vile Parle East, Kandivali, ShimpoliRegistered on MahaRERA as “RASHMI CELESTIA”
What’s in the report? →Possession date of Modi Rashmi Celestia (MahaRERA P51800051034): 31 October 2026, moved from 11 August 2025 (14 months later), and it has already passed. It has 64 homes (2 BHK, 3 BHK and 4 BHK, 586–1135 sq ft carpet), 93% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800051034, and currently active.
Source: MahaRERA website — records for P51800051034, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Modi Rashmi Celestia?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Modi Rashmi Celestia has moved
11 August 2025
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EA03092502500)
Reason the builder gave MahaRERA:
“The delay in the completion of the project is primarily due to prolonged timelines in obtaining mandatory statutory approvals from various government authorities. Although all required applications and supporting documents were submitted we…” Read the full reason
“The delay in the completion of the project is primarily due to prolonged timelines in obtaining mandatory statutory approvals from various government authorities. Although all required applications and supporting documents were submitted well within the stipulated timeframes, certain key approvals-including Municipal Building Plan Approval, Fire NUC, and other essential infrastructure-related permissiопз-were still pending. These approvals are critical prerequisites for initiating and continuing various stages of the construction process. The delays are administrative in nature and largely…”31 October 2026
Extended at the builder's request (MahaRERA application EA28072621901)
Reason the builder gave MahaRERA: “OC Recived”
Source: Modi Rashmi Celestia’s extension records on MahaRERA (P51800051034), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Modi Rashmi Celestia
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800051034
- Status
- Registered and active
- Builder
- Modi's Navnirman Limited
- Location
- Borivali West, Mumbai · 400092
- Project type
- Others
- Registered on
- 22 May 2023
- Completion date at registration
- August 2025
- Latest completion date
- October 2026
- Delay so far
- 14 months
- Homes
- 64
- Sold or booked
- 93%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of Modi Rashmi Celestia, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RASHMI CELESTIA | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- RASHMI CELESTIA: covers Basement + Ground Floor + 1 to 4 Podium Floor +5 to 17 upper floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Modi Rashmi Celestia every 1–2 months.
Modi Rashmi Celestia: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 586 – 820 | 39 |
| Shops | 139 – 3,411 | 20 |
| 3 BHK | 931 – 955 | 13 |
| 4 BHK | 1,102 – 1,135 | 12 |
- Buildings: RASHMI CELESTIA (19 floors, 84 units)
- Car parking: 132 covered
- Land: 2,162 sq m (about 0.5 acres) · sanctioned built-up 7,001 sq m
- Boundaries filed include: LOKMANYA TILAK ROAD
- Land, as filed: 125
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Modi's Navnirman (a group of 2 linked companies) has 12 projects on MahaRERA since 2021, this one included. Of the 12 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 3 months); 8 still being built, 3 past the promised date (typically 15 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Modi Rashmi Celestia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Modi Rashmi Celestia: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Modi Rashmi Celestia
What is the possession date of Modi Rashmi Celestia?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Modi Rashmi Celestia in Borivali West, Mumbai is 31 October 2026 — 14 months later than 11 August 2025, the date given at registration. That date has already passed.
The date has already moved 14 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Modi Rashmi Celestia?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Modi Rashmi Celestia's builder has filed on MahaRERA, the official one, is 31 October 2026, already 14 months later than the 11 August 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Modi Rashmi Celestia extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi Rashmi Celestia's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "The delay in the completion of the project is primarily due to prolonged timelines in obtaining mandatory statutory approvals from various government authorities. Although all required applications and supporting documents were submitted well within the stipulated timeframes, certain key approvals-including Municipal Building Plan Approval, Fire NUC, and other essential infrastructure-related permissiопз-were still pending. These approvals are critical prerequisites for initiating and continuing various stages of the construction process. The delays are administrative in nature and largely…"; to 31 October 2026, giving the reason "OC Recived".
What is the RERA number of Modi Rashmi Celestia?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Modi Rashmi Celestia in Borivali West, Mumbai is P51800051034.
Is Modi Rashmi Celestia registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi Rashmi Celestia is registered as P51800051034 and its status is "Registered and active".
What is the current construction status of Modi Rashmi Celestia? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi Rashmi Celestia's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RASHMI CELESTIA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Modi Rashmi Celestia have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Modi Rashmi Celestia safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi Rashmi Celestia is registered on MahaRERA as P51800051034, its completion date has moved 14 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Modi Rashmi Celestia?
Modi Rashmi Celestia is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Modi Rashmi Celestia are 586 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Modi Rashmi Celestia?
For a flat in Modi Rashmi Celestia (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Modi Rashmi Celestia received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Modi Rashmi Celestia is still under construction, with 31 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Modi Rashmi Celestia a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi Rashmi Celestia is a redevelopment: 44 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Modi Rashmi Celestia uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Modi Rashmi Celestia was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Modi Rashmi Celestia's possession date changes?
The latest dates are on Modi Rashmi Celestia's MahaRERA page (P51800051034). GharKundli's Kundli Watch sends a free WhatsApp update on Modi Rashmi Celestia every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Modi Rashmi Celestia have?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi Rashmi Celestia has one building filed: RASHMI CELESTIA with 19 floors and 84 units.
What are the flat sizes (carpet area) in Modi Rashmi Celestia?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Modi Rashmi Celestia: 2 BHK: 586 to 820 sq ft carpet (39 homes); 3 BHK: 931 to 955 sq ft carpet (13 homes); 4 BHK: 1102 to 1135 sq ft carpet (12 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Modi Rashmi Celestia have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 132 covered car parking spaces for Modi Rashmi Celestia.
How big is the land of Modi Rashmi Celestia?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi Rashmi Celestia stands on 2,162 sq m of land (about 0.5 acres), with 7,001 sq m of sanctioned built-up area.
What is the track record of Modi Rashmi Celestia's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi's Navnirman (a group of 2 linked companies) has 12 projects on MahaRERA since 2021, this one included. Of the 12 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 3 months); 8 still being built, 3 past the promised date (typically 15 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Modi Rashmi Celestia?
Google Maps has reviews of Modi Rashmi Celestia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Modi Rashmi Celestia?
Modi Rashmi Celestia by Modi's Navnirman Limited is in Borivali West, Mumbai, pincode 400092 (near Vile Parle East, Kandivali, Shimpoli), Maharashtra, and is registered on MahaRERA as P51800051034, per GharKundli's check of MahaRERA records. Its boundaries filed there include LOKMANYA TILAK ROAD. Its land is filed as 125. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).
How many flats are in Modi Rashmi Celestia, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi Rashmi Celestia has 64 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.
When was Modi Rashmi Celestia registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Modi Rashmi Celestia was registered on MahaRERA on 22 May 2023. GharKundli did not find a title report on the land on file there.
Does Modi Rashmi Celestia have any legal issues or court cases?
No court cases are listed for Modi Rashmi Celestia on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Modi Rashmi Celestia?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Modi's Navnirman Limited, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Modi Rashmi Celestia
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Borivali West (400092)
- Skylark Heights
- Gaurav Galaxy
- Soni Arcade, Building No 2
- Fortune Avirahi Wing A
- Shraddha Skyline
- Sparkle Umadarshan
- I Space Urban Vista
- Hiranandani Bluecrest
Other projects by Modi's Navnirman Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.