SAI KRUPA CHSL REDEVELOPED
by OSHO Developers · Babhai, Mumbai
Possession: SAI KRUPA CHSL REDEVELOPED is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800034596. Status: Completed.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAI KRUPA CHSL REDEVELOPED?
How the possession date of SAI KRUPA CHSL REDEVELOPED has moved
10 February 2026
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA30012619649)
Reason the builder gave MahaRERA: “this has reference”
Source: SAI KRUPA CHSL REDEVELOPED’s extension records on MahaRERA (P51800034596), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI KRUPA CHSL REDEVELOPED
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800034596
- Status
- Completed
- Builder
- OSHO Developers
- Location
- Babhai, Mumbai · 400091
- Project type
- Others
- Registered on
- 11 Apr 2022
- Completion date at registration
- February 2026
- Latest completion date
- June 2026
- Delay so far
- 4 months
- Homes
- 99
- Sold or booked
- 67%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of SAI KRUPA CHSL REDEVELOPED, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI KRUPA CHSL | 100% | 100% | 100% | 98% |
Commencement certificate (CC), as filed on MahaRERA
- SAI KRUPA CHSL: covers Basement + Ground + 1st + 2nd floor + 3rd to 5th podium + 6th floor to 30th + 31st (pt) upper floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI KRUPA CHSL REDEVELOPED every month.
SAI KRUPA CHSL REDEVELOPED: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 405 – 870 | 79 |
| 3 BHK | 603 – 1,050 | 20 |
| Shops | 497 – 563 | 3 |
- Buildings: SAI KRUPA CHSL (33 floors, 102 units)
- Car parking: 124 covered, 1 open
- Land: 2,755 sq m (about 0.7 acres) · sanctioned built-up 8,155 sq m · recreational space 551 sq m
- Boundaries filed include: Ram Mandir Road
The builder’s record and reviews
Osho Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 11 months). 2 complaints on MahaRERA across 1 project.
Read Google reviews of SAI KRUPA CHSL REDEVELOPED →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI KRUPA CHSL REDEVELOPED: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI KRUPA CHSL REDEVELOPED
What is the possession date of SAI KRUPA CHSL REDEVELOPED?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI KRUPA CHSL REDEVELOPED in Babhai, Mumbai is 30 June 2026 — 4 months later than 10 February 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SAI KRUPA CHSL REDEVELOPED?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI KRUPA CHSL REDEVELOPED's builder has filed on MahaRERA, the official one, is 30 June 2026, already 4 months later than the 10 February 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI KRUPA CHSL REDEVELOPED extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA CHSL REDEVELOPED's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "this has reference".
What is the RERA number of SAI KRUPA CHSL REDEVELOPED?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI KRUPA CHSL REDEVELOPED in Babhai, Mumbai is P51800034596.
Is SAI KRUPA CHSL REDEVELOPED registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA CHSL REDEVELOPED is registered as P51800034596 and its status is "Completed".
What is the construction status of SAI KRUPA CHSL REDEVELOPED?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA CHSL REDEVELOPED's status on MahaRERA is "Completed". As filed by the builder, slab work on SAI KRUPA CHSL is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SAI KRUPA CHSL REDEVELOPED have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SAI KRUPA CHSL REDEVELOPED safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA CHSL REDEVELOPED is registered on MahaRERA as P51800034596, its MahaRERA status is "Completed", its completion date has moved 4 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI KRUPA CHSL REDEVELOPED's possession date changes?
The latest dates are on SAI KRUPA CHSL REDEVELOPED's MahaRERA page (P51800034596). GharKundli's Kundli Watch sends a free WhatsApp update on SAI KRUPA CHSL REDEVELOPED every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI KRUPA CHSL REDEVELOPED have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA CHSL REDEVELOPED has one building filed: SAI KRUPA CHSL with 33 floors and 102 units.
What are the flat sizes (carpet area) in SAI KRUPA CHSL REDEVELOPED?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAI KRUPA CHSL REDEVELOPED: 2 BHK: 405 to 870 sq ft carpet (79 homes); 3 BHK: 603 to 1050 sq ft carpet (20 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SAI KRUPA CHSL REDEVELOPED have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 124 covered and 1 open car parking spaces for SAI KRUPA CHSL REDEVELOPED.
How big is the land of SAI KRUPA CHSL REDEVELOPED?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA CHSL REDEVELOPED stands on 2,755 sq m of land (about 0.7 acres), with 8,155 sq m of sanctioned built-up area and 551 sq m of recreational open space.
What is the track record of SAI KRUPA CHSL REDEVELOPED's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Osho Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 11 months). 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAI KRUPA CHSL REDEVELOPED?
Google Maps has reviews of SAI KRUPA CHSL REDEVELOPED written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI KRUPA CHSL REDEVELOPED?
SAI KRUPA CHSL REDEVELOPED by OSHO Developers is in Babhai, Mumbai (pincode 400091), Maharashtra, and is registered on MahaRERA as P51800034596, per GharKundli's check of MahaRERA records. Its boundaries filed there include Ram Mandir Road.
How many homes are in SAI KRUPA CHSL REDEVELOPED?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA CHSL REDEVELOPED has 99 homes in 1 tower registered on MahaRERA, and 67% of them are sold or booked.
When was SAI KRUPA CHSL REDEVELOPED registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA CHSL REDEVELOPED was registered on MahaRERA on 11 April 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI KRUPA CHSL REDEVELOPED?
No court cases are listed for SAI KRUPA CHSL REDEVELOPED on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAI KRUPA CHSL REDEVELOPED?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is OSHO Developers, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAI KRUPA CHSL REDEVELOPED
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Borivali
- PATKESHWAR APARTMENT CHS LTD
- SAFFRONWOODS CHSL
- L&T Realty Ahana Tower B
- L&T Realty Ahana Tower A
- PARSHURAM HEIGHTS
- AVIRAHI ELEGANCE
- MARU MANSION
- SHRADDHA SKYLINE
Other projects by OSHO Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.