Possession date of Shivoham Avyukta Jayesh (MahaRERA PM1180002500769): 31 July 2029. It has 49 homes (1 BHK, 2 BHK and 3 BHK, 391–2139 sq ft carpet), 45% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1180002500769, and currently active. Its completion date is now July 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PM1180002500769, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shivoham Avyukta Jayesh?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shivoham Avyukta Jayesh has moved

  1. 31 March 2029

    Completion date given when the project was registered

  2. 31 July 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shivoham Avyukta Jayesh’s extension records on MahaRERA (PM1180002500769), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shivoham Avyukta Jayesh

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1180002500769
Status
Registered and active
Builder
SHIVOHAM INFRAHOMES LLP
Location
Borivali, Mumbai · 400092
Project type
Mixed
Registered on
15 Sep 2025
Completion date at registration
March 2029
Latest completion date
July 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
49
Sold or booked
45%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Shivoham Avyukta Jayesh, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AVYUKTA JAYESH100%5%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • AVYUKTA JAYESH: covers plinth

Latest CC order on MahaRERA: dated 25/08/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shivoham Avyukta Jayesh every 1–2 months.

Shivoham Avyukta Jayesh: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK603 – 1,17317
2 BHK603 – 1,13317
Shops296 – 3,49114
4 BHK1,310 – 2,13913
1 BHK391 – 4462

The builder’s record and reviews

Shivoham Infrahomes (a group of 4 linked companies) has 12 projects on MahaRERA since 2021, this one included. Of the 12 GharKundli has checked: 4 finished, all within the promised date; 8 still being built, none past the promised date yet. 3 complaints on MahaRERA across 2 projects.

Read Google reviews of Shivoham Avyukta Jayesh →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shivoham Avyukta Jayesh: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shivoham Avyukta Jayesh

What is the possession date of Shivoham Avyukta Jayesh?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shivoham Avyukta Jayesh in Borivali, Mumbai is 31 July 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Shivoham Avyukta Jayesh?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shivoham Avyukta Jayesh's builder has filed on MahaRERA, the official one, is 31 July 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shivoham Avyukta Jayesh?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shivoham Avyukta Jayesh in Borivali, Mumbai is PM1180002500769.

Is Shivoham Avyukta Jayesh registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Avyukta Jayesh is registered as PM1180002500769 and its status is "Registered and active".

What is the current construction status of Shivoham Avyukta Jayesh? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Avyukta Jayesh's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AVYUKTA JAYESH is 5% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Shivoham Avyukta Jayesh have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shivoham Avyukta Jayesh safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Avyukta Jayesh is registered on MahaRERA as PM1180002500769, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shivoham Avyukta Jayesh?

Shivoham Avyukta Jayesh is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shivoham Avyukta Jayesh are 391 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shivoham Avyukta Jayesh?

For a flat in Shivoham Avyukta Jayesh (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shivoham Avyukta Jayesh received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Avyukta Jayesh is still under construction, with 31 July 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Shivoham Avyukta Jayesh a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Avyukta Jayesh is a redevelopment: 43 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Shivoham Avyukta Jayesh uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shivoham Avyukta Jayesh was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shivoham Avyukta Jayesh's possession date changes?

The latest dates are on Shivoham Avyukta Jayesh's MahaRERA page (PM1180002500769). GharKundli's Kundli Watch sends a free WhatsApp update on Shivoham Avyukta Jayesh every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shivoham Avyukta Jayesh have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Avyukta Jayesh has one building filed: AVYUKTA JAYESH with 20 floors and 63 units.

What are the flat sizes (carpet area) in Shivoham Avyukta Jayesh?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shivoham Avyukta Jayesh: 3 BHK: 603 to 1173 sq ft carpet (17 homes); 2 BHK: 603 to 1133 sq ft carpet (17 homes); 4 BHK: 1310 to 2139 sq ft carpet (13 homes); 1 BHK: 391 to 446 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Shivoham Avyukta Jayesh have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 119 covered car parking spaces for Shivoham Avyukta Jayesh.

How big is the land of Shivoham Avyukta Jayesh?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Avyukta Jayesh stands on 2,100 sq m of land (about 0.5 acres), with 7,034 sq m of sanctioned built-up area.

What is the track record of Shivoham Avyukta Jayesh's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Infrahomes (a group of 4 linked companies) has 12 projects on MahaRERA since 2021, this one included. Of the 12 GharKundli has checked: 4 finished, all within the promised date; 8 still being built, none past the promised date yet. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shivoham Avyukta Jayesh?

Google Maps has reviews of Shivoham Avyukta Jayesh written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shivoham Avyukta Jayesh?

Shivoham Avyukta Jayesh by SHIVOHAM INFRAHOMES LLP is in Borivali, Mumbai, pincode 400092 (near Eksar Village, Dahisar East, Daulat Nagar), Maharashtra, and is registered on MahaRERA as PM1180002500769, per GharKundli's check of MahaRERA records. Its boundaries filed there include 90FT WIDE CHANDAVARKAR ROAD. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).

How many flats are in Shivoham Avyukta Jayesh, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Avyukta Jayesh has 49 homes in 1 tower registered on MahaRERA, and 45% of them are sold or booked.

When was Shivoham Avyukta Jayesh registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivoham Avyukta Jayesh was registered on MahaRERA on 15 September 2025. GharKundli did not find a title report on the land on file there.

Does Shivoham Avyukta Jayesh have any legal issues or court cases?

No court cases are listed for Shivoham Avyukta Jayesh on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shivoham Avyukta Jayesh?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIVOHAM INFRAHOMES LLP, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Borivali West (400092)

All 362 projects in Borivali West (400092) →

Other projects by SHIVOHAM INFRAHOMES LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.